Edit a resource calendar

This topic is intended for the administrator who defines resource calendars.

  1. Choose Enterprise, Calendars, then choose Resource.
  2. Select the calendar you want to edit and click Modify.
  3. To base the calendar on another calendar, select a new global calendar in the Inherit Holidays and Exceptions from Global Calendar field.
  4. Choose the month you want to modify by clicking the appropriate arrow button next to the month-year title.
  5. To add a nonworkday, click the date you want to make a nonworkday, then click Nonwork.
  6. To change the number of hours in a specific workday, click the date you want to change.

    Choose Total work hours/day to define the total working hours in each day. In the Work hours/day section, set the amount of hours available to work for a specific day.

    Choose Detailed work hours/day to define which hours of the day are work or nonwork hours. In the Work hours section, select the hours you want to change and click Work or Nonwork.

    If the date's display color changes to white, the number of hours you entered does not equal the default number of working hours for that weekday.
  7. To make an exception into a workday and apply the default number of working hours to that day, click the exception you want to change, then click Standard.
  8. To define the calendar's default hours per timeperiod, click Time Periods.or each timeperiod, enter the default number of hours.

    For activities and resources to which the calendar is assigned, these values are used as conversion factors when users enter or display units and durations in time increments other than hours.

Tips

Note

Related Topics

Edit your personal resource calendar

Manual future period buckets

Future period bucket planning FAQ

Defining default hours per time period in calendars



Legal Notices | Your Privacy Rights
Copyright © 1999, 2021

Last Published Monday, December 6, 2021