A percent complete that is entered manually by the user instead of being calculated by the module is known as a "physical" percent complete.
The default method is to calculate percent complete according to activity duration.
- Choose Project, Activities.
- Select the activity whose physical percent complete you want to enter.
- Display Activity Details, then click the General tab.
- Select Physical as the percent complete type.
- Click the Status tab.
- In the Physical % field, type a physical percent complete.
Note
- You may enter a percent complete value for in progress activities only. If the activity has not started yet or has already finished, you will not be able to specify a percent complete value.