Enter activity constraints

  1. Choose Project, Activities, then select the activity whose constraint you want to define.
  2. Display Activity Details, then click the Status tab.
  3. In the Primary field, select a constraint type.
  4. Click in the Date field, then select the date to which the constraint applies.
  5. In the Secondary field, select a constraint type (if necessary).
  6. Click in the Date field, then select the date to which the constraint applies.

Notes

Related Topics