Level of effort activity

A level of effort activity’s duration is dependent on its predecessor and/or successor activities. Level of effort activities cannot have constraints assigned to them. Level of effort activities are not included when leveling resources.

Use level of effort activities for on-going tasks that depend on other activities. For example, you could assign level of effort activities for clerical work, a security guard, or even some aspects of project management.

A level of effort activity is similar to but different from a hammock activity.