Analyzing the resource-driven critical path

  1. Select an activity to analyze.
  2. Click Backward Resource Driven Critical Path.

    Click Increase Maximum Multiple Critical Path Count or Decrease Maximum Multiple Critical Path Count to view more or fewer resource-driven critical paths to the selected activity.

    Click Select Maximum Multiple Critical Path Count to specify the number of critical paths to show.

    Note: You can also view the activity-driven critical paths, with or without resource leveling. Click Forward Activity Critical Path, Backward Activity Critical Path, or Activity Critical Path to view the activity driven critical paths.