Relationships tab - Activity Details

Use this tab to view and manage predecessors and successors from a single Activity Details tab. To enlarge either the Predecessor or Successor area, drag the split bar separating the right and left panes. The Predecessor area functions identically to the Predecessor tab, and the Successor area functions identically to the Successor tab. The data stored on the Relationships tab is synchronized with that on the Predecessors and Successors tabs.

Predecessors

Project ID: Identifies the project.

WBS: Lists WBS codes for the selected activity's predecessors.

Activity ID: Lists activity IDs for the selected activity's predecessors.

Activity Name: Lists names of the selected activity's predecessors.

Relationship Type: Lists each predecessor's relationship type for the selected activity. To change a relationship type, double-click it. The following relationship types are available: finish to start, finish to finish, start to start, and start to finish.

Lag: Lists the lag time value associated with each of the selected activity's predecessor relationships. To change a lag time value, double-click it.

Activity Status: Lists the status of each of the selected activity's predecessors.

Primary Resource: Lists the primary resource for each of the selected activity's predecessors. The primary resource is the person responsible for the overall work on the activity.

Assign: Adds a predecessor to the selected activity.

Remove: Removes the selected predecessor from the selected activity.

Go To: Displays the selected predecessor activity's information.

Note

Successors

Project ID: Identifies the project.

WBS: Lists WBS codes for the selected activity's successors.

Activity ID: Lists activity IDs for the selected activity's successors.

Activity Name: Lists activity names of the selected activity's successors.

Relationship Type: Lists each successor's relationship type for the selected activity. The following relationship types are available: finish to start, finish to finish, start to start, and start to finish. To change a relationship type, double-click it.

Lag: Lists the lag time value associated with each of the selected activity's successor dependencies. To change a lag time value, double-click it.

Activity Status: Lists the status of each of the selected activity's successors.

Primary Resource: Lists the primary resource for each of the selected activity's successors.

Assign: Adds a successor to the selected activity.

Remove: Removes the selected successor from the selected activity.

Go To: Displays the selected successor activity's information.