Resource dependent activity

Resources assigned to this type of activity are scheduled to work according to the resources’ calendars rather than the activity’s calendar. The activity’s duration is determined by the availability of resources to work on the activity.

Use resource dependent activities when multiple resources assigned to the same activity can work independently.