Show or hide overtime information in the Resource Usage Profile

  1. In the Activities window, choose View, Show on Bottom, Resource Usage Profile.

    You can also click the Layout Options bar, then choose Show on Bottom, Resource Usage Profile.
  2. In the right pane of the bottom layout window, click the Display Options bar and make sure Show All Projects is not selected. A check next to Show All Projects indicates that it is selected.
  3. Click the Display Options bar again and choose Resource Usage Profile Options.

    You can also right-click in the profile and choose Resource Usage Profile Options.
  4. Click the Data tab.
  5. Mark or clear the Show Overtime checkbox.