Status tab - Activity Details

Use the Status tab to define the selected activity's duration, constraint, start and finish dates, labor and nonlabor units and costs, and material costs. You can also use the Status tab to view the selected activity's float, actuals, and completion percentages.

Duration

Original or Planned:Original or Planned: The expected number of work periods required to complete the selected activity. You can type a new time value and unit.

Actual: The actual number of workperiods spent on the selected activity. If the selected activity is complete, type a new number.

Remaining: The remaining number of workperiods needed to complete the selected activity. If the selected activity is in progress, type a new number.

At Complete: An estimate of the duration at completion time for the selected activity. (At Complete Duration = Actual Duration + Remaining Duration). If the selected activity is in progress, type a new at complete estimate.

Total Float: The amount of time the selected activity can be delayed, without delaying the project's finish date.

Free Float: The amount of time the selected activity can be delayed, without delaying the immediate successor activities.

Status

Started: Mark to indicate that the selected activity has started. The field beside this checkbox displays the activity's project planned start date. If the selected activity has started or is complete, this field displays the activity's actual start date. To select a start date, click  .

Finished: Mark to indicate that the selected activity is complete. The field beside this checkbox displays the activity's remaining finish date. If the selected activity is complete, this field displays the activity's actual finish date. To select the actual finish date, click  .

Exp Finish: The date the activity's primary resource expects the activity to end. Only the primary resource can edit this date.

When you add an Expected Finish date, the calendar defaults to the date and time of the activity's Early Finish date.

When you edit an Expected Finish date, the calendar defaults to the date and time that is currently in the Exp Finish field.

%: If the selected activity's percent complete type is set to Duration, the selected activity's duration percent complete is calculated from the Original or Planned and remaining duration.

If the selected activity's percent complete type is set to Units, this field displays the selected activity's unit percent complete, as calculated from the actual and remaining units.

If the selected activity's percent complete type is set to Physical, this field displays the selected activity's physical percent complete, which is manually entered.

If the selected activity's percent complete type is set to Scope, this field displays the selected activity's scope percent complete, which is calculated in Oracle Primavera Cloud. You cannot edit the activity's percent complete value if the percent complete type is set to Scope.

Note

Scope % (P6 EPPM only): The percent complete for the activity if the percent complete type is set to scope. Scope % is calculated in Oracle Primavera Cloud when P6 EPPM is integrated with Oracle Primavera Cloud for scope management.

Suspend: Enter the date on which the activity's progress stopped.

Note

Resume: Enter the date on which the suspended activity's progress resumed.

Constraints

Primary: The selected activity's primary constraint type: start on or after, start on or before, finish on, finish on or after, finish on or before, as late as possible, mandatory start, or mandatory finish. You can select a new type.

Date: The selected activity's constraint date. Click to select a new date.

Secondary: The selected activity's secondary constraint type. This list is filtered based on the value you select in the Primary field. You can select a new type.

Date: The selected activity's constraint date. Click to select a new date.

Note

(Non)Labor Units/(Non)Labor Cost/Material Cost

Budgeted or Planned: The expected number of labor or nonlabor units or cost, or material cost the selected activity will use, depending on your current display. You can type a new budgeted or planned value.

Actual: The actual number of labor or nonlabor units or cost, or material cost the selected activity has used, depending on your current display. If the selected activity has started, type a new actual value for units. You can enter actual cost on an activity that has not yet started.

Remaining: The remaining number of labor or nonlabor units or cost, or material cost the selected activity will use, depending on your current display. If the selected activity is in progress, type a new remaining value.

At Complete: An estimate of the labor or nonlabor units or cost, or material cost at the completion of the selected activity (At Complete Units(or Cost) = Actual Units(or Cost) + Remaining Units(or Cost)). If the selected activity is in progress, type a new At Complete estimate.