Successors tab - Activity Details

Use the Successors tab to add, edit, and remove successor relationships for the selected activity.

You can change the columns that display under the Successors tab. To change the displayed columns, right-click in the Successors table, then choose Customize Successor Columns.

Project ID: Identifies the project.

WBS: Lists WBS codes for the selected activity's successors.

Activity ID: Lists activity IDs for the selected activity's successors.

Activity Name: Lists activity names of the selected activity's successors.

Relationship Type: Lists each successor's relationship type for the selected activity. The following relationship types are available: finish to start, finish to finish, start to start, and start to finish. To change a relationship type, double-click it.

Lag: Lists the lag time value associated with each of the selected activity's successor dependencies. To change a lag time value, double-click it.

Activity Status: Lists the status of each of the selected activity's successors.

Primary Resource: Lists the primary resource for each of the selected activity's successors.

Assign: Adds a successor to the selected activity.

Remove: Removes the selected successor from the selected activity.

Go To: Displays the selected successor activity's information.