Suspend or resume an activity's progress

At some point in the project, you may need to stop work on an activity for a period of time. Indicate this interruption by specifying suspend and resume dates in the Status tab of Activity Details.

  1. Display Activity Details.
  2. Click the Status tab.
  3. In the Activities window, select the activity you want to suspend.
  4. In the Status tab, enter a Suspend date.

    When the activity resumes, enter a Resume date.

Tips

Notes