View activity relationships in the Activity Table

The Activity Table enables you to view the open project's activity information in table format.

  1. Choose View, Columns.

    You can also click the Layout Options bar and choose Columns.
  2. To view information about predecessors, select Predecessor Details in the Available Columns section, then click .
  3. To view information about successors, select Successor Details in the Available Columns section, then click .