Portfolio Manager: Cash Flow Budget Curves

Portfolio Cash Flow budget curves are part of the Cost Manager function. Users in the project can view Cash Flow budget curves from the Cash Flow node of the Cost Manager.

There are three Portfolio Cash Flow Budget Curves:

For example, an approved budget for the year 2015 might include a planned project for road construction that is scheduled to begin in 2017 with a budget of $100,000. The approved budget for the year 2016 will continue to include the planned road construction budget, with an addition of $15,000 to the forecasted budget. In the year 2017, the road construction project goes into execution, and the approved budget is $115,000. This figure becomes the original budget for the road construction project. From then on, as budget forecasting continues, the approved budget for the road construction will be the original budget, plus any changes that occur to the numbers during the life of that project.