Setting Up Gates

Before you begin: Verify the list of project phases resides in the Project Phase data definition pull-down data set. This is the same list that is used when selecting a project phase manually in the project properties window. You can add or modify the default list as needed. This list makes the phases available for any project or project template; for each project or template, you select which of the phases to use. Create any business processes that you plan to use to drive gates conditions and phase completion.

Step 1: Define Project Phases. For each project or template, you define the list of project phases to include in the setup, choosing from the entire list in the Project Phase data set.

Step 2: Define Gate Conditions. For each phase, define one or more gates conditions. A gate condition is a combination data element and trigger condition that enable transition to the next phase.

Step 3: Schedule Gates runs. The gates runs run the validation of gate conditions. You can schedule runs automatically. This is optional.

Step 4: Activate the gates setup.

Step 5: Define permissions.

Note: If you create a new project by copying a project template or an existing project, any existing gates setup in the source project is copied into the new project, including the gates status. The gates phases are restarted at the first phase in the new project, and the scheduled gates run is activated.

See Also

Welcome to Primavera Unifier

Getting Started with Unifier General Administration Guide

Security Considerations in Unifier

Companies in Unifier

Administrators in Unifier

Permission-Based Security in Unifier

Company Landing Page (Admin)

Program Landing Page (Admin)

Shell Landing Page (Admin)

Project Landing Page (Admin)

Queries

Dashboards in Unifier

Self-Service Portal

Access Control and AutoVue Stamps

Managing Public Searches

Adding & Managing Partner Companies

Manage Support and e-Learning contact information (Contact tab)

Manage Company Password Policy (Security tab)

Manage Company Addresses (Address tab)

Access Company Details (Edit Company Window)

Background Jobs

Event Notifications

uDesigner Overview

Custom Dashboards

User Administration

Program Administration

Unifier Activity Manager

Managing Personal Information in Unifier

Translating Custom Strings (Internationalization)

Configuring and Publishing BI Publisher Custom Templates (Custom Prints and Reports)

Configuring Project Numbering, Cost Codes, and Status

Configuring the User Mode Navigator

Unifier Mobile Application

Unifier and Other Oracle Applications

Copyright

Getting Started with Unifier Modules Setup Administration Guide

Creating Data Views

Creating Data Cubes

Shells Administration

Setting up the Automatic Update of Shell Status

How to Set up Gates

Editing Multiple Shells at once with Bulk Edit

Shell Dashboards

Setting up Data Structure Setup Node

Setting up Multiple Company Calendars

Setting up the Business Processes

Setting up Updates for Business Process Records

Setting up the Asset Manager

Setting up the Code-Based and Records-Based Configurable Manager

Setting up the Cost Manager

Setting up the Document Manager

Setting up the Planning Manager

Setting up the Portfolio Manager

Setting up the Resource Manager

Setting up the Schedule Manager

Setting up the Earned Value Management Permissions

Setting up the Space Manager

Setting up the User-Defined Reports

Configuration Package Management

Including Stamps in Configuration Package

Copyright

In This Section

Example of a gates setup and conditions

Define the project phase list

Create a gates setup

Add project phases to the gates setup (Settings tab)

Configure Gates conditions

Configure gate elements

Change the order of project phases

Define gates runs schedule (Schedule tab)

Activate or deactivate a gates setup

Set user permissions for gates



Legal Notices | Your Privacy Rights
Copyright © 1998, 2025

Last Published Tuesday, April 1, 2025