The following explains each of the manual activity sheet Schedule types:
Duration Based Schedules
- The Activity Sheet receives duration based information from P6
- (Not always) The Activity Sheet receives resource assignment related information
- (Not always) The Activity Sheet receives cost related information
- The Activity Sheet is not available as a source for Cash Flow and Cost Sheet
- The Activity Sheet does not have any cost related feature (Assign rate sheet and Recost)
- The Activity Sheet is not available for Earned Value Analysis
Cost Loaded Schedules
- The Activity Sheet receives the entire duration based information from P6
- The Activity Sheet receives the entire resource assignment related information
- The Activity Sheet receives the entire cost related information
- The Activity Sheet is available as a source for Cash Flow and Cost Sheet
- The Activity Sheet does not have any cost related feature (Assign rate sheet and Recost)
- The Activity Sheet is available for Earned Value Analysis
Resource Loaded Schedules
- The Activity Sheet receives the entire duration based information from P6
- The Activity Sheet receives the entire resource assignment related information
- (Not always) The Activity Sheet receives the entire cost related information
- The Activity Sheet is available as a source for Cash Flow and Cost Sheet
- The Activity Sheet has all cost related feature (Assign rate sheet and Recost)
- The Activity Sheet is available for Earned Value Analysis