To add a Baseline curve for cash flow by project or shell:
- Go to your project or shell (User mode).
This is the project or shell that contains the cash flow that you want.
- From the left Navigator, click the Cost Manager node to expand.
- Click the Cash Flow sub-node to open the Cash Flow log window (the Cash Flow log).
The Cash Flow log is the starting place for cash flow operations. The log displays all existing cash flow curves and also provides options for creating new curves, copying curves, viewing curve properties, and assigning curve usage privileges to other users.
- Select the cash flow from the Cash Flow log window.
- Click the gear menu and click the Properties option to open the Cash Flow Properties window (or the Cash Flow Properties worksheet).
- In the Cash Flow Properties window General pane, ensure that the Project/Shell option is selected from the Detail Level drop-down list. The options under the Detail Level drop-down list are:
- Project/Shell
- Summary CBS
- CBS
- Business Process (Commitments)
When you select the Project/Shell option in the Detail Level drop-down list, you have the option to filter for either the CBS Codes, or filter for the Summary CBS Codes.
- In the Cash Flow Properties window Curves pane, click the Curves drop-down list and select Baseline to open the Baseline window.
- Complete the fields in this window by using the following information. When finished click Save & Close to save your work and open the cash flow worksheet that you have added.
When you select the Project/Shell option in the Detail Level drop-down list (General pane) and in the Curves pane you add Baseline curve (from the Curves drop-down list), proceed to set up the following parameters:
Cost | Note: You can choose the cost column when creating a curve in a project or shell but not in templates. Select one of the following options:
|
---|---|
Schedule | Enables you to define the range of dates (what dates to start the curve and end the curve) to use to plot the cash flow data. Note: If you choose to take dates from the schedule sheet elements, then Unifier uses the Master schedule sheet for the project or shell. Select one of the following options for each date:
|
Distribution | Distribution profiles are used to distribute data automatically in the cash flow worksheet. This option enables you to select a distribution profile to use as the default distribution profile for the curve. Select one of the following options for how to distribute the data automatically between cash flow time periods:
The distribution profiles are defined in the:
The default profile is used for the initial display and calculations in the cash flow worksheet. You can change the distribution profile from the worksheet. If you do this, the default profile will automatically update to reflect the current selection. When you build a Baseline curve for individual line items, the Schedule of Value (SOV) type influences the distribution options.
|
Variance | Your choices are:
For Project/Shell, typically, the Variance is set to Inflow for a Baseline type curve. The value will be used to calculate variances against the Outflow type curves. |