You can copy an existing synchronization, and then edit the copy to create a new synchronization as needed.
Note: This is a quicker method to create a synchronization from an existing synchronization.
To copy a synchronization in Gateway:
- In the sidebar, select Synchronizations.
- Select the synchronization you want to copy, select the Actions menu, and then select Copy.
The Synchronization wizard displays a copy of the current synchronization.
- In the Flow and Deployments step:
- In the Synchronization Name field, rename the synchronization.
The default name of the duplicate synchronization is always created with the word, Copy. For example, Send Primavera Cloud Project Data to P6 Copy.
- From the Business Flow list, select a business flow that is to be used by the synchronization.
- The source and destination for data transfer are pre-selected. Update only if necessary.
Note: Select Next on each screen to advance to the next step.
- In the Synchronization Name field, rename the synchronization.
- In the Parameters step, edit the value of each parameter as needed.
- In the Summary step, review a summary of all the selections made in the previous steps.
Select any of the following actions:
- Select Back to navigate to a specific step and make changes.
- Select Save to add the synchronization.
The synchronization is now available for running on the Synchronizations page.