The following is an example of modifying a global calendar imported into P6:
The existing imported workweek is:
| Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday |
---|---|---|---|---|---|---|---|
Start and Stop Time |
| 8 to 5 | 8 to 5 | 8 to 5 | 8 to 5 | 8 to 5 |
|
The subsequent import is:
| Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday |
---|---|---|---|---|---|---|---|
Start and Stop Time |
|
| 9 to 3 | 9 to 3 | 9 to 3 |
|
|
After import, the workweek is:
| Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday |
---|---|---|---|---|---|---|---|
Start and Stop Time |
|
| 9 to 3 | 9 to 3 | 9 to 3 |
|
|
The following changes have been made:
- The existing work time for Monday and Friday have been removed.
- In the source calendar, Exception time (Holiday) is April 24, 2013 and workday exception is April 27, 2013 (Saturday).
- The incoming updates made to the calendar are: Holiday is April 26, 2013 and Workday exception is April 28, 2013 (Sunday).
Note: April 24, 2013 and April 26, 2013 are still exceptions as the exception list has been merged in the existing calendar.