WBSSpread

Description: Summarized spread data per WBS.

Field

Type

Description

Read-Only

ActualCost

Double

Actual Cost.

No

ActualExpenseCost

Double

Actual Expense Cost.

No

ActualLaborCost

Double

Actual Labor Cost.

No

ActualLaborUnits

Double

Actual Labor Units.

No

ActualMaterialCost

Double

Actual Material Cost.

No

ActualNonlaborCost

Double

Actual Nonlabor Cost.

No

ActualNonlaborUnits

Double

Actual Nonlabor Units.

No

ActualTotalCost

Double

Actual Total Cost.

No

AtCompletionExpenseCost

Double

At Completion Expense Cost.

No

AtCompletionLaborCost

Double

At Completion Labor Cost.

No

AtCompletionLaborUnits

Double

At Completion Labor Units.

No

AtCompletionMaterialCost

Double

At Completion Material Cost.

No

AtCompletionNonlaborCost

Double

At Completion Nonlabor Cost.

No

AtCompletionNonlaborUnits

Double

At Completion Nonlabor Units.

No

AtCompletionTotalCost

Double

At Completion Total Cost.

No

BaselinePlannedExpenseCost

Double

Baseline Planned Expense Cost.

No

BaselinePlannedLaborCost

Double

Baseline Planned Labor Cost.

No

BaselinePlannedLaborUnits

Double

Baseline Planned Labor Units.

No

BaselinePlannedMaterialCost

Double

Baseline Planned Material Cost.

No

BaselinePlannedNonlaborCost

Double

Baseline Planned Nonlabor Cost.

No

BaselinePlannedNonlaborUnits

Double

Baseline Planned Nonlabor Units.

No

BaselinePlannedTotalCost

Double

Baseline Planned Total Cost.

No

EarnedValueCost

Double

Earned Value Cost.

No

EarnedValueLaborUnits

Double

Earned Value Labor Units.

No

EndDate

DateTime

Spread end date.

No

EstimateAtCompletionCost

Double

Estimate At Completion Cost.

No

EstimateAtCompletionLaborUnits

Double

Estimate At Completion Labor Units.

No

EstimateToCompleteCost

Double

Estimate To Complete Cost.

No

EstimateToCompleteLaborUnits

Double

Estimate To Complete Labor Units.

No

ObjectId

String

The unique ID generated by the system.

No

PeriodActualCost

Double

Period Actual Cost.

No

PeriodActualExpenseCost

Double

Period Actual Expense Cost.

No

PeriodActualLaborCost

Double

Period Actual Labor Cost.

No

PeriodActualLaborUnits

Double

Period Actual Labor Units.

No

PeriodActualMaterialCost

Double

Period Actual Material Cost.

No

PeriodActualNonLaborCost

Double

Period Actual NonLabor Cost.

No

PeriodActualNonLaborUnits

Double

Period Actual NonLabor Units.

No

PeriodAtCompletionExpenseCost

Double

Period At Completion Expense Cost.

No

PeriodAtCompletionLaborCost

Double

Period At Completion Labor Cost.

No

PeriodAtCompletionLaborUnits

Double

Period At Completion Labor Units.

No

PeriodAtCompletionMaterialCost

Double

Period At Completion Material Cost.

No

PeriodAtCompletionNonLaborCost

Double

Period At Completion NonLabor Cost.

No

PeriodAtCompletionNonLaborUnits

Double

Period At Completion NonLabor Units.

No

PeriodAtCompletionTotalCost

Double

Period At Completion Total Cost.

No

PeriodEarnedValueCost

Double

Period Earned Value Cost.

No

PeriodEarnedValueLaborUnits

Double

Period Earned Value Labor Units.

No

PeriodEstimateAtCompletionCost

Double

Period Estimate At Completion Cost.

No

PeriodEstimateAtCompletionLaborUnits

Double

Period Estimate At Completion Labor Units.

No

PeriodPlannedValueCost

Double

Period Planned Value Cost.

No

PeriodPlannedValueLaborUnits

Double

Period Planned Value Labor Units.

No

PeriodType

String

The type of period for summarized spread data.

No

PlannedExpenseCost

Double

Planned Expense Cost.

No

PlannedLaborCost

Double

Planned Labor Cost.

No

PlannedLaborUnits

Double

Planned Labor Units.

No

PlannedMaterialCost

Double

Planned Material Cost.

No

PlannedNonlaborCost

Double

Planned Nonlabor Cost.

No

PlannedNonlaborUnits

Double

Planned Nonlabor Units.

No

PlannedTotalCost

Double

Planned Total Cost.

No

PlannedValueCost

Double

Planned Value Cost.

No

PlannedValueLaborUnits

Double

Planned Value Labor Units.

No

ProjectId

String

Project short name.

No

ProjectObjectId

ForeignKey

The unique ID of Project.

No

RemainingExpenseCost

Double

Remaining Expense Cost.

No

RemainingLaborCost

Double

Remaining Labor Cost.

No

RemainingLaborUnits

Double

Remaining Labor Units.

No

RemainingLateExpenseCost

Double

Remaining Late Expense Cost.

No

RemainingLateLaborCost

Double

Remaining Late Labor Cost.

No

RemainingLateLaborUnits

Double

Remaining Late Labor Units.

No

RemainingLateMaterialCost

Double

Remaining Late Material Cost.

No

RemainingLateNonlaborCost

Double

Remaining Late Nonlabor Cost.

No

RemainingLateNonlaborUnits

Double

Remaining Late Nonlabor Units.

No

RemainingLateTotalCost

Double

Remaining Late Total Cost.

No

RemainingMaterialCost

Double

Remaining Material Cost.

No

RemainingNonlaborCost

Double

Remaining Nonlabor Cost.

No

RemainingNonlaborUnits

Double

Remaining Nonlabor Units.

No

RemainingTotalCost

Double

Remaining Total Cost.

No

StartDate

DateTime

Spread start date.

No

WBSCode

String

WBS Code.

No

WBSObjectId

ForeignKey

The unique ID of WBS.

No