Description: CBS Sheet Row Cost fields.
Field | Type | Description | Read-Only |
---|---|---|---|
actualCostToDate | Double | The actual costs incurred on the scope assignment. This tracks the VOWD (Value of Work Done). | No |
actualCostToDateProject | Double | The actual cost to date of a project. | No |
actualRiskResponse | Double | The actual cost of implementing the response action. | No |
actualRiskResponseProject | Double | The pending manual budget of a project. | No |
adjustedCost | Double | The amount the scope assignment work that is not yet accounted for. For example, you might enter a value to represent pending change requests that are likely to be approved. | No |
adjustedCostProject | Double | The adjusted cost of a project. | No |
approvedChangedCost | Double | The sum of all approved cost changes in the change records for the scope assignment. | No |
approvedChangedCostProject | Double | The approved changed cost of a project. | No |
approvedManualBudget | Double | Calculated as the sum of all costs approved for the original manual budget. | No |
approvedManualBudgetChanges | Double | The total approved current manual budget of a project. Calculated as the sum of Approved Original Manual Budget plus Approved Manual Budget Changes plus Approved Manual Budget Transfers. | No |
approvedManualBudgetChangesProject | Double | Approved manual budget changes of a project. | No |
approvedManualBudgetProject | Double | Calculated as the sum of all costs approved for the manual budget. | No |
approvedManualBudgetTransfers | Double | Calculated as the sum of all approved manual budget transfers for the project. | No |
approvedManualBudgetTransfersProject | Double | Approved manual budget transfers of a project. | No |
approvedManualCurrentBudget | Double | The total approved current manual budget of a project. Calculated as the sum of Approved Original Manual Budget plus Approved Manual Budget Changes plus Approved Manual Budget Transfers. | No |
approvedManualCurrentBudgetProject | Double | Approved manual current budget of a project. | No |
approvedProjectActuals | Double | The total amount of confirmed actuals. | No |
atCompletionCost | Double | The total cost at the completion of the scope assignment. Calculated as Revised Cost plus Adjusted Cost. | No |
atCompletionCostProject | Double | Calculated as the sum of actual costs plus remaining costs for the project. | No |
bacCost | Double | The Revised Cost or At Completion Cost at the time the current baseline was set, depending on the selection for the Budget at Completion Method. The Revised Cost of the current project if no baseline is set. | No |
bacCostProject | Double | The BAC cost of a project. | No |
baselineCost | Double | The Revised Cost at the time the current baseline was set. | No |
baselineCostProject | Double | The baseline cost of a project. | No |
cbsSheetCodeId | String | The unique ID generated by the system. | No |
closedPostExposure | Double | The mean post-response probability of the risk multiplied by the mean post-response cost impact of the risk. | No |
closedPostExposureProject | Double | The mean post-response probability of a closed risk multiplied by the mean post-response cost impact of the risk. | No |
closedPreExposure | Double | The mean pre-response probability of the risk multiplied by the mean pre-response cost impact of the risk. | No |
currentBudget | Double | The total approved current manual budget of a project. Calculated as the sum of Approved Original Manual Budget plus Approved Manual Budget Changes plus Approved Manual Budget Transfers. | No |
currentBudgetProject | Double | Calculated as the sum of all current costs for the selected budget sources. Selected budget sources can include scope based budget and manual budget. | No |
eacCost | Double | Calculated as ETC Cost plus Actual Cost to Date. | No |
eacCostProject | Double | The EAC cost of a project. | No |
earnedCost | Double | Calculated as Performance Percent Complete multiplied by BAC Cost. | No |
earnedCostProject | Double | The earned cost of a project. | No |
etcCost | Double | The estimate of the cost needed to complete the work. Calculated as BAC Cost minus Earned Cost. | No |
etcCostProject | Double | The ETC cost of a project. | No |
installedCost | Double | The total cost incurred on the scope assignment as of the current date. If Rate By = Hours, then Installed Cost = Revised Cost Rate * Installed Hours. If Rate By = Quantity, then Installed Cost = Revised Cost Rate * Installed Quantity. | No |
installedCostProject | Double | The installed cost of a project. | No |
openPostExposure | Double | The mean post-response probability of the risk multiplied by the mean post-response cost impact of the risk. | No |
openPostExposureProject | Double | The mean post-response probability of an open risk multiplied by the mean post-response cost impact of the risk. | No |
openPreExposure | Double | The mean pre-response probability of the risk multiplied by the mean pre-response cost impact of the risk. | No |
openPreExposureProject | Double | The mean pre-response probability of an open risk multiplied by the mean pre-response cost impact of the risk. | No |
pendingChangedCost | Double | Calculated as the sum of all pending cost changes in the change records for the scope assignment. | No |
pendingChangedCostProject | Double | The pending changed cost of a project. | No |
pendingManualBudget | Double | Calculated as the sum of all costs pending for the original manual budget. | No |
pendingManualBudgetChanges | Double | Calculated as the sum of all pending manual budget changes for the project. | No |
pendingManualBudgetChangesProject | Double | Pending manual budget changes of a project. | No |
pendingManualBudgetProject | Double | The pending manual cost of a project. | No |
pendingManualBudgetTransfers | Double | Calculated as the sum of all pending manual budget transfers for the project. | No |
pendingManualBudgetTransfersProject | Double | Pending manual budget transfers of a project. | No |
pendingProjectActuals | Double | The total amount of pending actuals. | No |
pendingProjectActualsProject | Double | Total amount of pending actuals for a project. | No |
plannedCost | Double | The original cost of the scope assignment. If Rate By = Hours, OrigCost=OrigHrs*OrigCostRate. If entered manually, OrigCostRate=OrigCost/OrigHrs. If RateBy=Qty, OrigCost=OrigQty*OrigCostRate. If entered manually, OrigCostRate=OrigCost/OrigQty. | No |
plannedCostProject | Double | The planned cost of a project. | No |
plannedRiskResponse | Double | The estimated cost associated with implementing the response action. | No |
plannedRiskResponseProject | Double | The actual cost of implementing a response action for a project. | No |
projectActualCost | Double | Total costs accrued on a project within a given time period. The Actual Cost data for the project's life cycle is pulled from the P6 EPPM schedule. Actual Cost data is only available when the application is connected with P6 EPPM and is not editable. | No |
projectActualCostProject | Double | Calculated as the sum of the amount of each actual line item for a project. | No |
projectCPI | Double | The measure of a project's cost efficiency. A value of less than 1 indicates the project is over budget, while a value greater than 1 indicates the project is under budget. | No |
projectCPIProject | Double | The CPI cost of a project. | No |
projectEarnedCost | Double | The value of work performed on a project in reference to the approved budget for the project. The cost value used for the Earned Value Management of a project. | No |
projectEarnedCostProject | Double | The earned cost of a project. | No |
remainingCost | Double | The amount left to be spent. If Rate By set to Hours, then Remaining Cost equals Remaining Hours multiplied by Revised Cost Rate. If Rate By set to Quantity, then Remaining Cost equals Remaining Quantity multiplied by Revised Cost Rate | No |
remainingCostProject | Double | The remaining total cost for the project, including labor resources, nonlabor resources, and project expenses. | No |
revisedCost | Double | The Original Cost before the baseline is set. After the baseline is set, Revised Cost equals Original Cost plus Approved Change Cost. | No |
revisedCostProject | Double | The revised cost of a project. | No |