Description: There must be at least one assignment in each Assignments collection.
Field | Description | Read-Only |
---|---|---|
ActualCost | The actual cost incurred on the assignment. | No |
ActualFinish | The date on which the assignment was completed. | No |
ActualOvertimeCost | The actual overtime cost incurred on the assignment. | No |
ActualOvertimeWork | The actual amount of overtime work incurred on the assignment. | No |
ActualOvertimeWorkProtected | The duration through which actual overtime work is protected. | No |
ActualStart | If the task has started, the date work began on the task. | No |
ActualWork | The sum of the actual non-overtime and the overtime units worked by the resource on the task. | No |
ActualWorkProtected | The duration through which actual work is protected. | No |
ACWP | The actual cost of work performed on the assignment to-date. | No |
AssignmentCode | The code that identifies this assignment. | No |
AssnOwner | The name of the assignment owner. | No |
AssnOwnerGuid | The GUID of the assignment owner. | No |
AtCompletionUnits | The sum of the actual units and the remaining units for the resource assignment on the task. | No |
BaselineCost | The current cost of the assignment in the project baseline. | Yes |
BaselineFinishDate | The date the assignment is scheduled to be finished. | Yes |
BaselineStartDate | The planned start date for the assignment on the task. | Yes |
BaselineWork | The planned units of work for the resource assignment on the task. | Yes |
BCWP | The budgeted cost of work performed on the assignment to-date. | No |
BCWS | The budgeted cost of work performed on the assignment. | No |
BookingType | The booking type of the assignment. 1 = Commited, 2 = Proposed. | No |
BudgetCost | The budgeted amount for cost resources on this assignment. | No |
BudgetWork | The budgeted work amount for work or material resources on this assignment. | No |
Confirmed | Whether the Resource has accepted all of his or her assignments. | No |
Cost | The projected or scheduled cost of the assignment. | No |
CostRateTable | The cost rate tableused for the assignment. Values are 0 = Price/Unit, 1 = Price/Unit1, 2 = Price/Unit2, 3 = Price/Unit3, 4 = Price/Unit4, 5 = Price/Unit5. | No |
CostVariance | The difference between the cost and baseline cost for a resource. | No |
CreationDate | The date that the assignment was created. | No |
CV | The earned value cost variance. | No |
Delay | The time lag between the tasks remaining start date and the resource's remaining start date on the task. | No |
Finish | The finish date of the assignment. | No |
FinishVariance | The variance of the assignment finish date from the baseline finish date. | No |
FixedMaterial | Whether the consumption of the assigned maerial resource occurs in a single, fixed amount. | No |
HasFixedRateUnits | Whether the Units ar Fixed Rate. | No |
Hyperlink | The title of the hyperlink associated with the assignment. | No |
HyperlinkAddress | The hyperlink associated with the assignment. | No |
HyperlinkSubAddress | The document bookmark of the hyperlink associated with the assignment. | No |
LevelingDelay | The delay caused by leveling. | No |
LevelingDelayFormat | The format for expressing the duration of the delay. | No |
LinkedFields | Whether the project is linked to another OLE object. | No |
Milestone | Whether the assignment is a milestone. | No |
Name | The short code that uniquely identifies the project. | No |
Notes | The text notes associated with the assignment. | No |
ObjectId | The unique ID generated by the system. | No |
Overallocated | Whether the assignment is overallocated. | No |
OvertimeCost | The sum of the actual and remaining overtime cost of the assignment. | No |
OvertimeWork | The scheduled overtime work scheduled for the assignment. | No |
PeakUnits | The largest number of units that a resource is assigned to a task. | No |
PercentWorkComplete | The amount of work completed on the assignment. | No |
ProjectId | The short code that uniquely identifies the project. | Yes |
RateScale | The time unit for the usage rate of the material resource assignment. For example resource m1[5lbs/hr]. | No |
RegularWork | The amount of non-overtime work scheduled for the assignment. | No |
RemainingCost | The remaining projected cost of completing the assignment. | No |
RemainingOvertimeCost | The remaining projected overtime cost of completing the assignment. | No |
RemainingOvertimeWork | The remaining overtime work scheduled to complete the assignment. | No |
RemainingUnitsPerHour | The units per time required for the resource assignment to complete the task. | No |
RemainingWork | The remaining units of work to be performed by the resource on the task. | No |
ResourceId | The short code that uniquely identifies the project. | Yes |
ResourceObjectId | The unique identfiier for the resource assigned to the task. | No |
ResourceType | The resource type: 'Labor', 'Non-Labor', or 'Material'. | No |
ResponsePending | Whether a response has been assigned for a TeamAssign message. | No |
Resume | The date that the assignment resumed. | No |
Start | The start date for the task assignment. | No |
StartVariance | The variance of the assignment from the baseline start date. | No |
Stop | The date that the assignment was stopped. | No |
Summary | Whether the task is a summary task. | No |
SV | The earned value schedule variance, through the project status date. | No |
TaskId | The short ID that uniquely identifies the task within the project. | Yes |
TaskObjectId | The unique ID of the task to which the resource is assigned. | No |
TaskType | The type of the task either 'Task Dependent', "Resource Dependent', 'Level of Effort', or 'Milestone'. | Yes |
UID | The unique identifier of the assignment. | No |
Units | The number of units for the assignment. | No |
UpdateNeeded | Whether the resource assigned to a task needs to be updated as to the status of the task. | No |
VAC | The difference between baseline cost and total cost. | No |
Work | The sum of the actual units and remaining units for the resource assignment on the task. | No |
WorkContour | The work contour of the assignment. Values are: 0 = Flat, 1 = Back, 2 = Front Loaded, 3 = Double Peak, 4 = Early Peak, 5 = Late Peak, 6 = Bell, 7 = Turtle, 8 = Contoured. | No |
WorkVariance | The variance of assignment work from the baseline work as minutes x 1000. | No |