This is a project data field mapping template for a duration-based Schedule Type, to create or update the master as well as the baseline Summary Sheets in Unifier. The following fields are mapped:
Unifier | Gateway | P6 |
---|---|---|
Title | ProjectName | ProjectName |
BaselineType | BaselineType | BaselineType |
DataDate | DataDate | DataDate |
PlannedStart | SummaryPlannedStartDate | SummaryPlannedStartDate |
PlannedFinish | SummaryPlannedFinishDate | SummaryPlannedFinishDate |
ActualStart | SummaryActualStartDate | SummaryActualStartDate |
ActualFinish | SummaryActualFinishDate | SummaryActualFinishDate |
RemainingStart | SummaryRemainingStartDate | SummaryRemainingStartDate |
RemainingFinish | SummaryRemainingFinishDate | SummaryRemainingFinishDate |
PlannedDuration | SummaryPlannedDuration | SummaryPlannedDuration |
RemainingDuration | SummaryRemainingDuration | SummaryRemainingDuration |
ActualDuration | SummaryActualDuration | SummaryActualDuration |
PercentComplete | SummaryPercentComplete | SummaryPercentComplete |