Project, Activity, and Resource codes can be extracted from P6 EPPM and loaded into Primavera Data Warehouse.

To configure P6 EPPM codes for Primavera Data Warehouse:

  1. In the Codes screen, select a code as follows:
    1. In the Available list box, select the code you want to extract.

      The list of available codes will be populated based on the P6 EPPM database connection that you set up in the previous screen for an Oracle database.

    2. Click the > right-arrow button to move the code to the Selected list box on the right.

      If this is the first time that you are running the configuration utility, the Selected list box is initially empty.

  2. To deselect codes:
    1. In the Selected list box, select the code you want to remove.
    2. Click the < left-arrow button to move the code to the Available list box on the left.
  3. Repeat the above steps for each code you want to extract or remove to finalize the list of codes.

    Primavera Data Warehouse has a limit of 240 codes for each supported type (Project, Activity, and Resource).

  4. Click Next after selecting all the required codes.

    See Configuring P6 EPPM User-Defined Fields for Primavera Data Warehouse to continue the configuration process.

Additional Information on Codes