Loading P6 EPPM Codes to Data Warehouse

To extract and load a subset of P6 EPPM Codes to Primavera Data Warehouse:

  1. Sign in to the Primavera Analytics Web Administration Application.
  2. In the side bar:
    1. Click staretl<id> for a specific data source.
    2. Click icon Codes.
  3. Select any of the following tabs to extract and load the following P6 EPPM codes to Primavera Data Warehouse:
    • Project
    • Activity
    • Resource

      Note: Primavera Data Warehouse has a limit of 240 codes for each supported type (Project, Activity, and Resource). By default, Primavera Analytics exposes only the codes that have been enabled through the Primavera Data Warehouse Configuration Utility or the Primavera Analytics Administration Web Application.

  4. To select a code to be loaded to Primavera Data Warehouse:
    1. In the Available Codes list, select a code.
    2. Click the right-arrow button to move the selected code to the.Enabled Codes list.
    3. Use the up and down arrow buttons to change the order of the codes in the ID column.
    4. Select Save Changes.
  5. To deselect a code:
    1. In the Enabled Codes list, select a code.
    2. Click the left-arrow button to move the selected code to the.Available Codes list.
    3. Select Save Changes.

      Note: The Primavera Analytics Web Administration Application cannot configure codes for a Primavera Unifier data source. Primavera Unifier code configuration is done within Primavera Unifier. See the Primavera Unifier documentation for details.