# | P6 field name in dropdown | P6 field name in Power Client | Data Type |
|---|---|---|---|
1 | AddActualToRemaining | Add Actual To Remain | Flag |
2 | AddedBy | Added By | Text |
3 | AnnualDiscountRate |
|
|
4 | AnticipatedFinishDate | Anticipated Finish | Date |
5 | AnticipatedStartDate | Anticipated Start | Date |
6 | CheckOutDate | Date Checked Out | Date |
7 | ContainsSummaryData | Contains Summary Data | Flag |
8 | ContainsSummaryDataOnly | Contains Summarized Data Only | Flag |
9 | CreateDate |
|
|
10 | CreateUser |
|
|
11 | CurrentBudget | Current Budget | Cost |
12 | CurrentVariance | Current Variance | Cost |
13 | DataDate | Data Date | Date |
14 | DateAdded | Date Added | Date |
15 | DiscountApplicationPeriod |
|
|
16 | DistributedCurrentBudget | Distributed Current Budget | Cost |
17 | EarnedValueETCUserValue |
|
|
18 | EarnedValueUserPercent |
|
|
19 | EstimatedWeight |
|
|
20 | FinishDate | Finish | Date |
21 | FiscalYearStartMonth |
|
|
22 | ForecastFinishDate | Forecast Finish Date | Date |
23 | ForecastStartDate | Forecast Start Date | Date |
24 | HasFutureBucketData |
|
|
25 | IndependentETCLaborUnits | Independent ETC Labor Units | Integer |
26 | IndependentETCTotalCost | Independent ETC Total Cost | Cost |
27 | LastSummarizedDate | Last Summarized Date | Date |
28 | LastUpdateDate |
|
|
29 | LastUpdateUser |
|
|
30 | LevelingPriority | Project Leveling Priority | Integer |
31 | MustFinishByDate | Must Finish By | Date |
32 | Name | Project Name | Text |
33 | OBSName | Resposinble Manager | Text |
34 | OriginalBudget | Original Budget | Cost |
35 | OverallProjectScore |
|
|
36 | PlannedStartDate | Planned Start | Date |
37 | ProjectForecastStartDate | Project Forecast Start | Date |
38 | ProposedBudget | Proposed Budget | Cost |
39 | RiskLevel | Risk Level | ValueList |
40 | ScheduledFinishDate |
|
|
41 | StartDate | Start | Date |
42 | Status | Project Status | ValueList |
43 | StrategicPriority | Strategic Priority | Special |
44 | SummaryAccountingVarianceByCost | Accounting Variance | Cost |
45 | SummaryAccountingVarianceByLaborUnits | Accounting Variance - Labor Units | Integer |
46 | SummaryActivityCount | Total Activities | ActivitesRelated |
47 | SummaryActualDuration | Actual Duration | Integer |
48 | SummaryActualExpenseCost | Actual Expense Cost | Cost |
49 | SummaryActualFinishDate | Actual Finish | Date |
50 | SummaryActualLaborCost | Actual Labor Cost | Cost |
51 | SummaryActualLaborUnits | Actual Labor Units | Integer |
52 | SummaryActualMaterialCost | Actual Material Cost | Cost |
53 | SummaryActualNonLaborCost | Actual Nonlabor Cost | Cost |
54 | SummaryActualNonLaborUnits | Actual Nonlabor Units | Integer |
55 | SummaryActualStartDate | Actual Start | Date |
56 | SummaryActualThisPeriodCost |
|
|
57 | SummaryActualThisPeriodLaborCost | Actual This Period Labor Cost | Cost |
58 | SummaryActualThisPeriodLaborUnits | Actual This Period Labor Units | Integer |
59 | SummaryActualThisPeriodMaterialCost | Actual This Period Material Cost | Cost |
60 | SummaryActualThisPeriodNonLaborCost | Actual This Period Nonlabor Cost | Cost |
61 | SummaryActualThisPeriodNonLaborUnits | Actual This Period Nonlabor Units | Integer |
62 | SummaryActualTotalCost | Actual Total Cost | Cost |
63 | SummaryActualValueByCost |
|
|
64 | SummaryActualValueByLaborUnits |
|
|
65 | SummaryAtCompletionDuration | At Completion Duration | Integer |
66 | SummaryAtCompletionExpenseCost | At Completion Expense Cost | Cost |
67 | SummaryAtCompletionLaborCost | At Completion Labor Cost | Cost |
68 | SummaryAtCompletionLaborUnits | At Completion Labor Units | Integer |
69 | SummaryAtCompletionMaterialCost | At Completion Material Cost | Cost |
70 | SummaryAtCompletionNonLaborCost | At Completion Nonlabor Cost | Cost |
71 | SummaryAtCompletionNonLaborUnits | At Completion Nonlabor Units | Integer |
72 | SummaryAtCompletionTotalCost | At Completion Total Cost | Cost |
73 | SummaryAtCompletionTotalCostVariance |
|
|
74 | SummaryBaselineCompletedActivityCount | BL Project Completed Activities | ActivitesRelated |
75 | SummaryBaselineDuration | BL Project Duration | Integer |
76 | SummaryBaselineExpenseCost | BL Project Expense Cost | Cost |
77 | SummaryBaselineFinishDate | BL Project Finish | Date |
78 | SummaryBaselineInProgressActivityCount | BL Project In-Progress Activities | ActivitesRelated |
79 | SummaryBaselineLaborCost | BL Project Labor Cost | Cost |
80 | SummaryBaselineLaborUnits | BL Project Labor Units | Integer |
81 | SummaryBaselineMaterialCost | BL Project Material Cost | Cost |
82 | SummaryBaselineNonLaborCost | BL Project Nonlabor Cost | Cost |
83 | SummaryBaselineNonLaborUnits | BL Project Nonlabor Units | Integer |
84 | SummaryBaselineNotStartedActivityCount | BL Project Not-Started Activities | ActivitesRelated |
85 | SummaryBaselineStartDate | BL Project Start | Date |
86 | SummaryBaselineTotalCost | BL Project Total Cost | Cost |
87 | SummaryBudgetAtCompletionByCost | Budget At Completion | Cost |
88 | SummaryBudgetAtCompletionByLaborUnits | Budget At Completion (BAC) - Labor Units | Integer |
89 | SummaryCompletedActivityCount | Actual Completed Activities | ActivitesRelated |
90 | SummaryCostPercentComplete | Cost % Complete | PercentComplete |
91 | SummaryCostPercentOfPlanned | Cost % Of Planned | PercentComplete |
92 | SummaryCostPerformanceIndexByCost | Cost Performance Index | Unkown |
93 | SummaryCostPerformanceIndexByLaborUnits | Cost Performance Index - Labor Units | Unkown |
94 | SummaryCostVarianceByCost | Cost Variance | Cost |
95 | SummaryCostVarianceByLaborUnits | Cost Variance - Labor Units | Integer |
96 | SummaryCostVarianceIndex |
|
|
97 | SummaryCostVarianceIndexByCost | Cost Variance Index | Unkown |
98 | SummaryCostVarianceIndexByLaborUnits | Cost Variance Index - Labor Units | Unkown |
99 | SummaryDurationPercentComplete |
|
|
100 | SummaryDurationPercentOfPlanned | Duration % Of Planned | PercentComplete |
101 | SummaryDurationVariance |
|
|
102 | SummaryEarnedValueByCost | Earned Value Cost | Cost |
103 | SummaryEarnedValueByLaborUnits | Earned Value - Labor Units | Integer |
104 | SummaryEstimateAtCompletionByCost | Estimate At Completion Cost | Cost |
105 | SummaryEstimateAtCompletionByLaborUnits | Estimate At Completion - Labor Units | Integer |
106 | SummaryEstimateAtCompletionHighPercentByLaborUnits |
|
|
107 | SummaryEstimateAtCompletionLowPercentByLaborUnits |
|
|
108 | SummaryEstimateToCompleteByCost | Estimate To Complete | Cost |
109 | SummaryEstimateToCompleteByLaborUnits | Estimate To Complete - Labor Units | Integer |
110 | SummaryExpenseCostPercentComplete | Expense Cost % Complete | PercentComplete |
111 | SummaryExpenseCostVariance | Variance - BL Project Expense Cost | Cost |
112 | SummaryFinishDateVariance |
|
|
113 | SummaryInProgressActivityCount | Actual In-Progress Activities | ActivitesRelated |
114 | SummaryLaborCostPercentComplete | Labor Cost % Complete | PercentComplete |
115 | SummaryLaborCostVariance | Variance - BL Project Labor Cost | Cost |
116 | SummaryLaborUnitsPercentComplete | Labor Units % Complete | PercentComplete |
117 | SummaryLaborUnitsVariance | Variance - BL Project Labor Units | Integer |
118 | SummaryMaterialCostPercentComplete | Material Cost % Complete | PercentComplete |
119 | SummaryMaterialCostVariance | Variance - BL Project Material Cost | Cost |
120 | SummaryNonLaborCostPercentComplete | Nonlabor Cost % Complete | PercentComplete |
121 | SummaryNonLaborCostVariance | Variance - BL Project Nonlabor Cost | Cost |
122 | SummaryNonLaborUnitsPercentComplete | Nonlabor Units % Complete | PercentComplete |
123 | SummaryNonLaborUnitsVariance | Variance - BL Project Nonlabor Units | Integer |
124 | SummaryNotStartedActivityCount | Actual Not-Started Activities | ActivitesRelated |
125 | SummaryPerformancePercentCompleteByCost |
|
|
126 | SummaryPerformancePercentCompleteByLaborUnits |
|
|
127 | SummaryPlannedValueByCost |
|
|
128 | SummaryPlannedValueByLaborUnits |
|
|
129 | SummaryProgressFinishDate |
|
|
130 | SummaryRemainingDuration | Remaining Duration | Integer |
131 | SummaryRemainingExpenseCost | Remaining Expense Cost | Cost |
132 | SummaryRemainingFinishDate |
|
|
133 | SummaryRemainingLaborCost | Remaining Labor Cost | Cost |
134 | SummaryRemainingLaborUnits | Remaining Labor Units | Integer |
135 | SummaryRemainingMaterialCost | Remaining Material Cost | Cost |
136 | SummaryRemainingNonLaborCost | Remaining Nonlabor Cost | Cost |
137 | SummaryRemainingNonLaborUnits | Remaining Nonlabor Units | Integer |
138 | SummaryRemainingStartDate |
|
|
139 | SummaryRemainingTotalCost | Remaining Total Cost | Cost |
140 | SummarySchedulePercentComplete |
|
|
141 | SummarySchedulePercentCompleteByLaborUnits |
|
|
142 | SummarySchedulePerformanceIndexByCost |
|
|
143 | SummarySchedulePerformanceIndexByLaborUnits |
|
|
144 | SummaryScheduleVarianceByCost | Schedule Variance | Cost |
145 | SummaryScheduleVarianceByLaborUnits | Schedule Variance - Labor Units | Integer |
146 | SummaryScheduleVarianceIndex |
|
|
147 | SummaryScheduleVarianceIndexByCost |
|
|
148 | SummaryScheduleVarianceIndexByLaborUnits |
|
|
149 | SummaryStartDateVariance |
|
|
150 | SummaryToCompletePerformanceIndexByCost | To Complete Performance Index | Unkown |
151 | SummaryTotalCostVariance |
|
|
152 | SummaryTotalFloat |
|
|
153 | SummaryUnitsPercentComplete |
|
|
154 | SummaryVarianceAtCompletionByLaborUnits | Variance At Completion - Labor Units | Integer |
155 | TotalBenefitPlan | Total Benefit Plan | Cost |
156 | TotalBenefitPlanTally | Total Benefit Plan Tally | Cost |
157 | TotalFunding | Total Funding | Cost |
158 | TotalSpendingPlan | Total Spending Plan | Cost |
159 | TotalSpendingPlanTally | Total Spending Plan Tally | Cost |
160 | UnallocatedBudget | Unallocated Budget | Cost |
161 | UndistributedCurrentVariance | Undistributed Current Variance | Cost |
162 | WebSiteRootDirectory | Web Site Root Directory | Text |
163 | WebSiteURL | Project Web Site URL | Text |
