For each task, you can schedule:
- How often the task should run.
- The date and time when the next run should occur.
The Schedule Tasks dialog box lists the tasks. When you select a task, the schedule for that task, including when the task will next be run, appears to the right of the task list.
You can select multiple tasks to assign a common schedule to those selected tasks. If you select multiple tasks, the only schedule information that appears, is that which is common to all the selected tasks.
When the Schedule Tasks application starts, the schedule is checked to determine which tasks need to run.
The following table lists the default schedule for the various PPM tasks.
Task | Default schedule |
---|---|
Import Data | Daily at 12:02 AM |
Standard Periodic Update (Portfolios) | Daily at 12:04 AM |
Frequent Periodic Update (Portfolios) | Receives new default task definition from PPM |
Custom Periodic Update (Portfolios) | Receives new custom task definition from PPM |
|
|
|
|
Recalculate Big Table Statistics | Daily at 12:11 AM |
Resolve Version Dates | Daily at 12:08 AM |
Database Maintenance Daily | Daily at 12:09 AM |
Active Directory Sync | Every half hour (30 minutes) |
Cell History Maintenance | Daily at 12:10 AM |
Log Files Maintenance | Daily at 12:05 AM |
Calculations using "Today" | Daily at 12:03 AM |
Audit Log Cleanup | Daily at 12:07 AM |
Switch Temp Tables | Every half hour (30 minutes) |
Recalculate Temp Table Statistics | Every half hour (30 minutes) |
Recalculate DB statistics | Daily at 12:06 AM |