Defining Phase Modified Events

You can define a Phase Modified event. This event type generates an alert whenever one or more of the following fields is modified in any of the phases relating to the specified item(s):
Status, % Complete, Health, Planned Start, Planned End, Forecast Start, Forecast End, Actual Start, Actual End.

It is possible to automatically create a Phase Modified alert. For more information refer to Creating a Specific Phase Alert.

To define a Phase Modified event:

  1. Select Phase Modified from the Event drop-down list.
  2. Select any of the following options to set the scope of the alert. Depending on your choice, different scope options become available:
    • Entire System: The following three options are available:
      • For any item: Check off this option to trigger an alert whenever any phase of any item throughout the entire system is modified.
      • For any portfolio: Check off this option to trigger an alert whenever any phase of any portfolio throughout the entire system is modified.
      • Both item and portfolio: Check off both options to trigger an alert whenever any phase of any item and/or any portfolio throughout the entire system is modified.

        Note: The Entire System option is visible only to authorized users. For more information on authorized users refer to Security.

    • Root (Items and Portfolios) Folder: The alert is triggered whenever a phase within any item or portfolio in the root is modified.
    • Portfolio (of portfolios): The following two options are available:
      • For the selected portfolio: The alert is triggered whenever a phase is modified within the selected portfolio.
      • For any portfolio in the selected portfolio: The alert is triggered whenever a phase is modified within any of the portfolios in the selected portfolio.
    • Portfolio (of items): The following two options are available:
      • For the selected portfolio: The alert is triggered whenever a phase is modified within the selected portfolio.
      • For any item in the selected portfolio: The alert is triggered whenever a phase is modified within an item in the selected portfolio.
    • Item: The alert is triggered whenever any phase is modified within the item.

Related Topics

Step 3: Defining Event Information

Defining Item/Portfolio Added to Portfolio Events

Defining Category Value Condition Met Events

Defining Category Indicator Condition Met Events

Defining Multiple Category Conditions Met Events

Defining Deliverable Modified Events

Defining Action Item Modified Events



Legal Notices | Your Privacy Rights
Copyright © 1998, 2020

Last Published Thursday, December 10, 2020