Activity Manager Permissions
You can use the following options to grant permission to Activity Sheet under the Activity Manager node.
Access Control
To update permissions for Activity Sheet at the company level:
- Go to the Company Workspace tab and switch to Admin mode.
- In the left Navigator, select User Administration, and then select Access Control.
- In the right pane, expand User Mode Access, expand Projects/Shells, expand Schedule Management, and select Activity Sheet.
To update permissions for Activity Sheet for a specific project/shell:
- Go to the shell tab and switch to Admin mode.
- In the left Navigator, select Access Control.
- In the right pane, expand User Mode Access, expand Schedule Management, and select Activity Sheet.
Grant any of the following available permissions:
- Get Data: If enabled, the user can invoke Get Data for the system Activity Sheet, which will update the system Activity Sheet from P6.
When enabled, the View permission is automatically enabled. If you clear the View permission, the system clears the Get Data permission. You cannot assign the Get Data permission without the View permission, but you can assign the View permission without the Get Data permission.
- Send Data
- View: If enabled, the user can view the Activity Sheet node along with the activity sheets present in that node (if any).
For Rate Sheet:
- Go to the Company Workspace tab and switch to Admin mode.
- In the left Navigator, select User Administration, and then select Access Control.
- In the right pane, expand User Mode Access, expand Projects/Shells, and select Rate Sheet.
Grant any of the following available permissions:
- Full Access
- Create: If enabled, the user can create a Rate Sheet.
- View: If enabled, the user can view the Rate Sheet node at Company Workspace.
Permission Templates
For Activity Sheet:
- Go to the Company Workspace tab and switch to Admin mode.
- In the left Navigator, select Standards & Libraries, and then select Permission Templates.
- Open the template, click the Permissions tab, and assign permissions.
- Under Modules For section, expand User Mode Access, expand Projects/Shells, expand Activity Manager, and select Activity Sheet.
- Assign permissions. See the description of permissions under Access Control, above.
For Rate Sheet:
- Go to the Company Workspace tab and switch to Admin mode.
- In the left Navigator, select Standards & Libraries, and then select Permission Templates.
- Open the template, click the Permissions tab, and assign permissions.
- Under Modules For section, expand User Mode Access, expand Projects/Shells, expand Activity Manager, and select Rate Sheet.
- Assign permissions. See the description of permissions under Access Control, above.