Change cost sheet currency
You can view cost sheet data in the company base currency or the project/shell currency, which may differ.
Note: This is also applicable to work packages and worksheets.
To choose the display currency on a cost sheet or worksheet:
- Open the project/shell Cost Sheet or worksheet window.
- From the Edit menu, click Currency and choose the currency from the list.
To choose the display currency on a work package:
- Open the work package window.
- Click the currency drop-down list in the upper right corner of the sheet and choose the currency from the list.
Last Published Monday, April 14, 2025