Project Status Business Process

The Project Status is typically filled in by the owner's project manager or owner's representative to report project health, status, trends, and risks to key stakeholders.

Characteristics

This is a Project-level business process with a workflow, provided in the system template.

Record Statuses

Approved

terminal status

Canceled

terminal status

Rejected

terminal status

Awaiting_Review

non-terminal status

Pending_Approval

non-terminal status

Sent_for_Revision

non-terminal status

Workflow

The default workflow for the Project Status business process is set up in a certain way; however, it may be used differently by your organization. Typically, a user with the necessary permissions can create the record and either move it directly to the end step or send it to others for review or approval. The recipients in the second step can approve or reject the record or send it on to others.

Creating a Project Status Record

Create a Project Status record by navigating to Project Management / Project Status on the Project/Shell tab, or from the Tasks log on the Home tab or relevant Project/Shell tab. Act on an existing Project Status task that has been assigned to you from the Tasks log.

Complete the Project Status form and attach related documents, if needed. After completing the form, click Send and select an action in the Workflow Actions list to determine the next step in the workflow. Click Send to route the form to the next assignee.

Note: You must enter a value in all required fields (*) before you can save the form.

  1. Go to your Project tab and switch to User mode.
  2. In the left Navigator, select Project Management, and then select Project Status.
  3. On the Project Status page, click Create. Refer to the tables below to complete the form. You can click Save at any time to save a draft version of the form. Draft versions are stored under Drafts.
  4. To add attachments, click Attach Files on the Attachments tab.
  5. After completing the form, click Send.
  6. On the Workflow Action Details tab, select who should receive this Project Status.
    • If permitted, you can add users to the CC list. These users will receive a notification about this Project Status but are not assigned a task.
    • If permitted, you can adjust task due dates for all users, or set individual task due dates for each assignee.
  7. Click Send.
  8. In the Notification window, review the content and click OK.

    The record moves to the next step in the workflow.

Completing the Project Status Form

Key Information

Key information about this Project Status is provided below.

Field Name

Access

Description

Title

Required

Enter a title.

Project Phase (Manual)

Editable

The phase for this project

Project % Complete

Editable

Percent complete for the overall project. This is entered manually and can be based on duration, costs, or progress.

Project Reporting

Reporting date and overall summary of the project Status

Field Name

Access

Description

Project Reporting Date

Required

The date the project status refers to

Project Reporting Summary

Required

Brief description of the current project report

Project Reporting Detailed Summary

Editable

Detailed description of the status of the project at the time of reporting

Project Status Summary

Enter a summary of the information related to the following items.

Field Name

Access

Description

Budget Status

Editable

The status of the project in relation to the budget

Budget Summary

Editable

Brief description of the budget status for the project-status period

Schedule Status

Editable

The status of the project in relation to the schedule

Schedule Summary

Editable

Brief description of the schedule status for the project-status period

Cost Status

Editable

The status of the project in relation to the expected cost

Cost Summary

Editable

Brief description of the cost status for the project-status period

Risk Status

Editable

Indicate the risk designation for the project. This value updates the Project details.

Risk Summary

Editable

Brief description of the risk status for the project status period

Project Analysis and Plans

This block should provide an indication of what has been done during the last project status period and what will be done in the next period.

Field Name

Access

Description

Work Completed Last Period

Editable

Brief description of the work that has been completed since the last project-status period

Opportunities and Challenges

Editable

Brief description of the opportunities and challenges for the report period

Recommended Actions

Editable

Brief description of the recommended actions to take during the next report period

Plans for Next Project Status Period

Editable

Brief description of the plans to complete for the next report period

Project Images

Add pictures showing the progress on this project, which will be included in the formal project status report. Additional images and documents can be added to the Attachments tab.

Field Name

Access

Description

Image 1

Editable

The attached Image #1.

Image 2

Editable

The attached image #2.

(Manual) Project Dates

These dates come from the Manual Project Dates block on the Project Details form and will update the Project Details form on approval of this Project Status record. If the project is linked to the Schedule on the Project Details, update the project Activity Sheet instead.

Field Name

Access

Description

Project Start Date

Editable

The actual start date of the project

Project End Date

Editable

The actual end date of the project

Project Planned Start Date

Editable

The planned start date for the project

Project Planned End Date

Editable

The planned end date for the project

Schedule Dates

Dates dynamically linked to the Schedule Dates block on the Project Details form that reflect the Activity Sheet in the project.

Field Name

Access

Description

Start Activity Name

Read-Only

Activity Name of the selected Start Activity/Milestone

Finish Activity Name

Read-Only

Activity Name of the selected Finish Activity/Milestone

Schedule Planned Start Date

Read-Only

Planned start date for the project, from the selected schedule activity/milestone

Schedule Planned End Date

Read-Only

Planned end date for the project, from the selected schedule activity/milestone

Schedule Actual Start Date

Read-Only

Actual start date for the project, from the selected schedule activity/milestone

Schedule Actual End Date

Read-Only

Actual end date for the project, from the selected schedule activity/milestone

Schedule Start Date

Read-Only

Start date for the project, from the selected schedule activity/milestone

Schedule End Date

Read-Only

Finish date for the project, from the selected schedule activity/milestone

Record Information

System information about this record

Field Name

Access

Description

Record Number

Read-Only

System-assigned record number

Status

Read-Only

Record status for a workflow BP record is based on the workflow action preceding the current workflow step.

Creator

Read-Only

Creator of this record

Creation Date

Read-Only

Date that the record was created

Record Last Update Date

Read-Only

Date that the record was last updated

Business Process Record URL

Read-Only

A shareable link to this record, for anyone with the necessary permissions

Project Name

Read-Only

Name of the project

Project Number

Read-Only

Unique Project Number

Additional Information

The Project Status Additional Information block is reserved for future use by your organization.

Field Name

Access

Description

Project Status Date Picker UDF 1

Disabled

Reserved for future use by your organization

Project Status Date Picker UDF 2

Disabled

Reserved for future use by your organization

Project Status Decimal UDF 1

Disabled

Reserved for future use by your organization

Project Status Decimal UDF 2

Disabled

Reserved for future use by your organization

Project Status Date Only Picker UDF 1

Disabled

Reserved for future use by your organization

Project Status Date Only Picker UDF 2

Disabled

Reserved for future use by your organization

Project Status Picker UDF 1

Disabled

Reserved for future use by your organization

Project Status Picker UDF 2

Disabled

Reserved for future use by your organization

Additional Notes

The Project Status Additional Notes block is reserved for future use by your organization.

Field Name

Access

Description

Project Status Text 255 UDF 1

Disabled

Reserved for future use by your organization

Project Status Text 255 UDF 2

Disabled

Reserved for future use by your organization

Project Status Text 255 UDF 3

Disabled

Reserved for future use by your organization

Project Status Text 255 UDF 4

Disabled

Reserved for future use by your organization

Project Status Long Text UDF 1

Disabled

Reserved for future use by your organization

Project Status Long Text UDF 2

Disabled

Reserved for future use by your organization



Last Published Monday, April 14, 2025