Risk Business Process

Use the Risk business process to record and prioritize all the risks that can occur in a project, and to propose and track the status of potential risks. Score risks using the risk matrix for both pre- and post-response plans.

Characteristics

This is a Project-level business process without a workflow, provided in the system template.

Record Statuses

Active

non-terminal status

Impacted

non-terminal status

Managed

non-terminal status

Open

non-terminal status

Proposed

non-terminal status

Rejected

non-terminal status

Related Processes

The Risk business process might create the following business processes: Action Item, Issue

The Risk business process might be created by the following business processes: Request for Information

Creating a Risk Record

Create a Risk record by navigating to Project Management / Risk on the Project/Shell tab, or from the Tasks log on the Home tab or relevant Project/Shell tab.

Complete the Risk form and attach related documents, if needed. After completing the form, click Save to create a record and keep it in editable mode, or click Submit if you are done and ready to commit the record.

Note: You must enter a value in all required fields (*) before you can save the form.

  1. Go to your Project tab and switch to User mode.
  2. In the left Navigator, select Project Management, and then select Risk.
  3. On the Risk page, click Create. Refer to the tables below to complete the form. You can click Save at any time to create a record and keep it in editable mode.
  4. To add attachments, click Attach Files on the Attachments tab.
  5. After completing the form, click Submit.

Completing the Risk Form

Key Information

Key information about this Risk is provided below.

Field Name

Access

Description

Title

Required

Title of the record

Status

Required

Required Risks initially begin with a Proposed status until they are reviewed. Following a review, they can be set to either Open (identified as a valid risk) or Rejected (not a valid risk). After the risk impacts the project, it should be set to Active. From there, it can either become Managed (it was successfully managed by the project team) or Impacted (it impacted the project).

Risk Type

Required

The type of risk for risk process

Risk Priority

Editable

The Risk Priority list from the drop-down list

Risk Category

Editable

The Risk Category list from the drop-down list

Contract

Editable

The contract that is a reference to this record

Pre-Response Probability of Occurrence

Editable

The probability of the risk occurring, before mitigation actions are taken

Cost Exposure

Read-Only

Determines cost exposure through multiplying the potential cost amount by the pre-response probability for the risk

Description

This information might appear in any formal printouts of this item.

Field Name

Access

Description

Short Description

Editable

Enter a description of 250 characters or fewer.

Cost & Schedule Information

Estimate the impact this risk will have on the cost and schedule.

Field Name

Access

Description

Cost Impact

Editable

Indicates whether there is a cost impact

Schedule Impact

Editable

Indicates whether there is a schedule impact

Owner Estimate

Editable

If there is a cost impact, this field shows the total amount of the cost impact.

Est. Schedule Impact (Days)

Editable

If the schedule is impacted, this field indicates the number of days that impact the schedule.

Cost Impact Notes

Editable

If there is a cost impact, this field describes the reason.

Schedule Impact Notes

Editable

Description of why the schedule is impacted, if a schedule impact is indicated

Action to Resolve

Enter information about how this Risk will be resolved.

Field Name

Access

Description

Proposed Action to Resolve

Editable

The proposed actions to resolve the risk

Actual Action to Resolve

Editable

The actions that must be taken to resolve the risk

Forecasted Resolution Date

Editable

The date when the issue threat has been eliminated, is no longer present, or is resolved independently

Actual Resolution Date

Editable

Actual date of Issue Resolution

Planned Response Cost

Editable

The risk planned response cost

Actual Response Cost

Editable

The actual cost to respond to the risk

Post-Response Probability of Occurrence

Editable

The probability of the risk occurring, after mitigation actions are taken

Issue Record

Read-Only

Link to the created Issue record, after it is created from a Risk record

Detailed Description

Enter a detailed summary of the cause, description, and effect of this risk.

Field Name

Access

Description

Cause

Editable

The cause or source of the risk

Description

Editable

Description for risk process

Effect

Editable

The effect for risk process

Risk Identification and Management

Information about the identification and management of the Risk

Field Name

Access

Description

Identified By

Editable

The person who has identified the risk

Identified Date

Editable

The date the risk was identified

Risk Manager

Editable

The person currently assigned to manage the risk

Exclude from Reporting?

Editable

Used to exclude this record from some project or organizational reports

Risk Exposure Window

Date range to define when the Risk might occur

Field Name

Access

Description

Start Date

Editable

The start date if the risk can only occur as of a specific date (for example, weather events)

Finish Date

Editable

The finish date if the risk can only occur until a specific date (for example, weather events)

Risk Matrix / Risk Scoring

This block can be used to calculate a score for this risk, based on the weightings set for this project.

Field Name

Access

Description

Cost Impact Weighting

Read-Only

The weighting for the cost impact when calculating the risk score

Pre-Response Cost Impact

Editable

The likely cost impact of the risk before response

Post-Response Cost Impact

Editable

The likely cost impact of the risk after response

Schedule Impact Weighting

Read-Only

The weighting for the schedule impact when calculating the risk score

Pre-Response Schedule Impact

Editable

The likely schedule impact of the risk before response

Post-Response Schedule Impact

Editable

The likely schedule impact of the risk after response

Scope Impact Weighting

Read-Only

The weighting for the scope impact when calculating the risk score

Pre-Response Scope Impact

Editable

The likely scope impact of the risk before response

Post-Response Scope Impact

Editable

The likely scope impact of the risk after response

Reputation Impact Weighting

Read-Only

The weighting for the reputation impact when calculating the risk score

Pre-Response Reputation Impact

Editable

The likely reputation impact of the risk before response

Post-Response Reputation Impact

Editable

The likely reputation impact of the risk after response

Environmental Impact Weighting

Read-Only

The weighting for the environmental impact when calculating the risk score

Pre-Response Environmental Impact

Editable

The likely environmental impact of the risk before response

Post-Response Environmental Impact

Editable

The likely environmental impact of the risk after response

Pre-Response Risk Score

Read-Only

The pre-response risk score is calculated from the pre-response criteria, based on the weightings specified for the project.

Post-Response Risk Score

Read-Only

The post-response risk score is calculated from the post-response criteria, based on the weightings specified for the project.

Record Information

System information about this record

Field Name

Access

Description

Record Number

Read-Only

System-assigned record number

Creator

Read-Only

Creator of this record

Creation Date

Read-Only

Date that the record was created

Record Last Update Date

Read-Only

Date that the record was last updated

Business Process Record URL

Read-Only

A shareable link to this record, for anyone with the necessary permissions

Project Name

Read-Only

Name of the project

Project Number

Read-Only

Unique Project Number

Related Activity/Milestone

Schedule information of the selected activity/milestone

Field Name

Access

Description

Activity/Milestone

Editable

Select the activity or milestone that should be used to track the planned and actual dates in this record.

Activity Name

Read-Only

The name of the selected activity/milestone from Project Schedule

Planned Start

Read-Only

The planned start date from the selected activity/milestone

Planned Finish

Read-Only

The planned finish date from the selected activity/milestone

Actual Start

Read-Only

The actual start date for the project from the schedule activity/milestone

Actual Finish

Read-Only

The actual finish date from the selected activity/milestone

Additional Information

The Risk Additional Information block is reserved for future use by your organization.

Field Name

Access

Description

Risk Date Picker UDF 1

Disabled

Reserved for future use by your organization

Risk Date Picker UDF 2

Disabled

Reserved for future use by your organization

Risk Decimal UDF 1

Disabled

Reserved for future use by your organization

Risk Decimal UDF 2

Disabled

Reserved for future use by your organization

Risk Date Only Picker UDF 1

Disabled

Reserved for future use by your organization

Risk Date Only Picker UDF 2

Disabled

Reserved for future use by your organization

Risk Currency Amount UDF 1

Disabled

Reserved for future use by your organization

Risk Currency Amount UDF 2

Disabled

Reserved for future use by your organization

Risk Picker UDF 1

Disabled

Reserved for future use by your organization

Risk Picker UDF 2

Disabled

Reserved for future use by your organization

Additional Notes

The Risk Additional Notes block is reserved for future use by your organization.

Field Name

Access

Description

Risk Text 255 UDF 1

Disabled

Reserved for future use by your organization

Risk Text 255 UDF 2

Disabled

Reserved for future use by your organization

Risk Text 255 UDF 3

Disabled

Reserved for future use by your organization

Risk Text 255 UDF 4

Disabled

Reserved for future use by your organization

Risk Long Text UDF 1

Disabled

Reserved for future use by your organization

Risk Long Text UDF 2

Disabled

Reserved for future use by your organization

Currency

If the currency of this Risk is different from the project currency, specify it here.

Field Name

Access

Description

Transaction Currency

Editable

If there are multiple currencies defined, use this field to specify a currency other than the project currency.

Rate in Project Currency

Read-Only

Exchange rate that will be used to calculate the Project Currency Amount. This will be set after the record is saved, submitted, or sent forward in the workflow. After it is set for a record, it cannot be changed.

Project Currency Amount

Read-Only

This field shows the amount of the transaction, according to the project currency.

Consolidating Line Items

Risk line items can be consolidated from the following business processes:

Completing the Detailed Cost Estimate tab

Cost Information

Cost breakdown for this risk. The Potential Cost Impact should be entered as a positive number. When calculating the Cost Exposure, Threats will appear as a positive number and Opportunities will appear as negative.

Field Name

Access

Description

Cost Code

Required

Enter a cost code.

Code Name

Read-Only

Populates the code name of the selected cost code

Potential Cost Impact

Required

The full potential cost impact of the risk line item, not taking probability into account

Cost Exposure

Read-Only

Determines cost exposure through multiplying the potential cost amount by the pre-response probability for the risk.

Description

Description for this Risk line item

Field Name

Access

Description

Short Description

Required

Enter a description of 250 characters or fewer.

Detailed Line Item Description

Editable

Enter additional detailed information about the line item description field.

Risk Information

Information from the Risk record. Updates to the Risk should be reflected here as well.

Field Name

Access

Description

Risk Type

Required

The type of risk for risk process

Pre-Response Probability of Occurrence

Required

The probability of the risk occurring, before mitigation actions are taken

Additional Information

Enter additional information specific to this Risk line item.

Field Name

Access

Description

Spend Category

Editable

Select the spending category.

Work Package

Editable

Select the Work Package that this item will roll up to.

Completing the Response Actions tab

Key Information

Key information for this response action

Field Name

Access

Description

Title

Required

Title of the record

Response Action Status

Required

Tracks the status of the response action

Assigned To

Editable

The action item will be assigned to this user for resolution on the next step of the workflow.

Key Dates

Planned and Actual dates for the response action

Field Name

Access

Description

Planned Start

Editable

Planned start date of the response action

Planned Finish

Editable

Planned finish date of the response action

Start

Editable

Start date of the response action

Finish

Editable

Finish date of the response action

Description

Enter a brief description of the response action and provide further details on the detailed description field.

Field Name

Access

Description

Short Description

Editable

Enter a description of 250 characters or fewer.

Detailed Description

Editable

The detailed information about the short-description field. The field size can be expanded.

Action Item

Create an Action Item on a given date, assigned to the response action manager above.

Field Name

Access

Description

Create Action Item?

Required

Determines whether an action item should be created for this record or line item

Create Action Item On

Required

Date when the Action Item should be created

Target Completion Date

Editable

The target completion date for the action item. To be updated as needed, particularly when re-assigning an action item.

Action Item Priority

Editable

An integer value representing the priority of the action item

Action Item Record

Editable

Link to the created Action Item record, after it is created