Estimate Business Process

Use the Estimate business process to create multiple project estimates, which can then be consolidated into the project's Initial Budget. Multiple scenarios can be built and compared.

The ORACLE PROJECT TEMPLATE includes an Estimate cash flow curve. Project Managers, Project Administrators, and Project Coordinators who have the necessary permissions can use the Master Schedule activity sheet to populate cash flow dates. The summarized Estimate amount will come from the Approved Estimates column on the Project Cost Sheet. Predefined distribution curves are available, or costs can be spread manually. Using the Estimate cash flow curve facilitates capital planning before an Initial Budget is created, which subsequently creates a Forecast cash flow curve.

Characteristics

This is a Project-level business process without a workflow, provided in the system template.

Record Statuses

Approved

terminal status

Active

non-terminal status

Discarded

non-terminal status

Informal

non-terminal status

Proposed

non-terminal status

Scenario_1

non-terminal status

Scenario_2

non-terminal status

Scenario_3

non-terminal status

Scenario_4

non-terminal status

Scenario_5

non-terminal status

Related Processes

The Estimate business process might create the following business processes: Initial Budget

The Estimate business process might be created by the following business processes: Project Request (Note that this is created through use of BP Data Transfer.)

Creating an Estimate record

Create an Estimate record by navigating to Budget Management / Estimate on the Project/Shell tab, or from the Tasks log on the Home tab or relevant Project/Shell tab.

Complete the Estimate form and attach related documents, if needed. After completing the form, click Save to create a record and keep it in editable mode, or click Submit if you are done and ready to commit the record.

Note: You must enter a value in all required fields (*) before you can save the form.

  1. Go to your Project tab and switch to User mode.
  2. In the left Navigator, select Budget Management, and then select Estimate.
  3. On the Estimate page, click Create. Refer to the tables below to complete the form. You can click Save at any time to create a record and keep it in editable mode.
  4. To add attachments, click Attach Files on the Attachments tab.
  5. After completing the form, click Submit.

Completing the Estimate Form

Key Information

Key information about this Estimate record

Field Name

Access

Description

Title

Editable

Enter a title.

Amount

Read-Only

Amount of this record or line item

Estimate Type

Editable

The type of the estimated budget

Estimate Category

Editable

The category for the estimated budget

Create an Initial Budget on Approval?

Editable

If selected, the system automatically creates an initial budget record after the estimated budget is approved.

Note: Excluded line items are not included in the initial budget record.

Estimate Version

Editable

This field is optional. If a previous budget estimate has been rejected or canceled, increment the version in this field.

Status

Required

Estimates typically begin as Informal and move to Active after they are prepared for review. They then move to Proposed before either being set to Approved or Discarded. After the Estimate is set to Approved, it can no longer be changed. You can also use the various Scenarios to compare different options.

Description

Enter a scope description, assumptions, justification, and anything else needed for this Estimate.

Field Name

Access

Description

Short Description

Editable

Enter a description of 250 characters or fewer.

Detailed Description

Editable

The detailed information about the short-description field. The field size can be expanded.

Estimate Units

Use the fields below to specify how this Estimate will be built. The selections here will be used for new line items that are added but can be changed per line item. The Project Total GSF and NASF are included for information purposes.

Field Name

Access

Description

Project Total GSF

Read-Only

The total Gross Square Footage (GSF) of the areas involved in the project scope

Project Total NASF

Read-Only

The total Net Assignable Square Footage (NASF) of the areas involved in the project scope

Unit of Measure

Editable

Enter the Unit of Measure used for the Unit Quantity and Cost Per Unit amounts.

Unit Quantity

Editable

Unit quantity to be used to calculate the Cost Per Unit for this record

Cost per Unit

Read-Only

The total cost divided by the unit quantity for this record

Record Information

System information about this record

Field Name

Access

Description

Record Number

Read-Only

System-assigned record number

Business Process Record URL

Read-Only

A shareable link to this record, for anyone with the necessary permissions

Creator

Read-Only

Creator of this record

Creation Date

Read-Only

Date that the record was created

Record Last Update Date

Read-Only

Date that the record was last updated

Due Date

Editable

Target completion date for this record. A default duration has been set by your administrator but can be overridden here for this record.

Project Number

Read-Only

Unique Project Number

Project Name

Read-Only

Name of the project

Additional Information

The Additional Information block is reserved for future use by your organization.

Field Name

Access

Description

Budget Date Picker UDF 1

Disabled

Reserved for future use by your organization

Budget Date Picker UDF 2

Disabled

Reserved for future use by your organization

Budget Decimal UDF 1

Disabled

Reserved for future use by your organization

Budget Decimal UDF 2

Disabled

Reserved for future use by your organization

Budget Date Only Picker UDF 1

Disabled

Reserved for future use by your organization

Budget Date Only Picker UDF 2

Disabled

Reserved for future use by your organization

Budget Currency Amount UDF 1

Disabled

Reserved for future use by your organization

Budget Currency Amount UDF 2

Disabled

Reserved for future use by your organization

Budget Picker UDF 1

Disabled

Reserved for future use by your organization

Budget Picker UDF 2

Disabled

Reserved for future use by your organization

Additional Notes

The Additional Notes block is reserved for future use by your organization.

Field Name

Access

Description

Budget Text 255 UDF 1

Disabled

Reserved for future use by your organization

Budget Text 255 UDF 2

Disabled

Reserved for future use by your organization

Budget Text 255 UDF 3

Disabled

Reserved for future use by your organization

Budget Text 255 UDF 4

Disabled

Reserved for future use by your organization

Budget Long Text UDF 1

Disabled

Reserved for future use by your organization

Budget Long Text UDF 2

Disabled

Reserved for future use by your organization

Currency

If the currency of this Estimate is different from the project currency, specify it here.

Field Name

Access

Description

Transaction Currency

Editable

If there are multiple currencies defined, use this field to specify a currency other than the project currency.

Rate in Project Currency

Read-Only

Exchange rate that should be used to calculate the Project Currency Amount. This will be set after the record is saved, submitted, or sent forward in the workflow. After it is set for a record, it cannot be changed.

Project Currency Amount

Read-Only

This field shows the amount of the transaction, according to the project currency.

Consolidating Line Items

Estimate line items can be consolidated from the following business processes:

Completing the Line Items tab

General

Specify a cost code for this Estimate line item.

Field Name

Access

Description

Cost Code

Required

Enter a cost code.

Code Name

Read-Only

Populates the code name of the selected cost code

Budget Details

Enter the cost for this line item as a lump sum or a unit rate. Note that excluded lines will have their amounts zeroed out.

Field Name

Access

Description

Item Quantity

Required

Enter the item quantity.

Unit of Measure

Editable

The default unit of measure used for any line items that are added to this record

Item Unit Cost

Required

Enter the item unit cost.

Amount

Read-Only

Amount of this line item

Description

Enter additional information specific to this Estimate line item.

Field Name

Access

Description

Short Description

Required

Enter a description of 250 characters or fewer.

Detailed Line Item Description

Editable

Enter additional detailed information about the line item description field.

Additional Information

Enter additional information specific to this Estimate line item.

Field Name

Access

Description

Exclude?

Editable

Exclude the line item amount but keep the line item in the record for informational purposes.

Spend Category

Editable

The spending category

Work Package

Editable

Select the Work Package that this item will roll up to.

Budget Line Item UDF PD 1

Disabled

Reserved for future use by your organization

Budget Line Item UDF Text 255 1

Disabled

Reserved for future use by your organization

Budget Line Item UDF CA 1

Disabled

Reserved for future use by your organization

Budget Line Item UDF DA 1

Disabled

Reserved for future use by your organization