Return to a Previous Phase
To return to a previously completed phase and set it as the current phase:
- Go to the shell tab and switch to User mode.
- In the left Navigator, select Gates.
- In the right column, do one of the following:
- Select a gate condition and deselect the Complete checkbox so that it is no longer complete.
- In Admin mode, add a new condition so that the completed phases are no longer complete. To do so, you must deactivate the gate, add the new condition, and then activate the gate. For more information, see How to Set Up Gates in the Unifier Essentials Modules Administration Guide.
- When you are done, click Save.