Activity Sheet

Release 24.01

New Schedule Comparison Custom Report

A new Schedule Comparison custom report has been added. Two Activity Sheets with common activity ID numbers may be selected and compared. Columns display start date, finish date, and duration for each activity, along with a color-coded Gantt chart.

Implementation Note: This enhancement is included in Configuration Package. An administrator will need to update the Project/Shell navigator and grant permissions for the report.

Image of a schedule comparison setup screen, where the master schedule is being compared to a contractor provided schedule.

Image of a schedule comparison report, showing a Gantt chart with different-colored lines representing the original master schedule and the revised contractor-provided schedule.



Last Published Monday, December 23, 2024