Configuring Services for Dual Path HA

This section provides the procedure for updating Oracle Communications User Data Repository Services for the Dual Path HA feature. This procedure applies to all configurations that make use of a Secondary/DR Site.

Note:

You must perform this configuration after completing the UDR Software Upgrade.
To configure services for dual path high availability:
  1. Login to UDR.
  2. From the main menu, select Configuration and then select Services.


  3. Click Edit and perform the following:
    1. For HA_Secondary service, in the Inter-NE HA_Secondary column, select XMI from the drop-down menu.


    2. Click Apply.
    3. Click OK in the popup window.

      NOAMP and MP Servers need to be restarted. The following Services Configuration screen appears.



  4. Restart/Reboot all NOAMP and MP Servers by doing one of the following:
    • From the main menu, select Status & Manage and then Server. The Server screen appears. Click Reboot.

    • Run the following reboot command on the terminal of each server:$ sudo reboot

      Note:

      You must execute the reboot command on all NOAMPs and MPs.
You have successfully configured services for dual path HA.