Scheduling ETL Runs
To schedule a ETL process run for a data source:
- Select a data source
- Sign in to the CIC Administration application.
http://<host>:<port>/cicadmin
- From the
Home menu, select a data source such as P6 or Aconex.
- In the sidebar, click
Status.
- Sign in to the CIC Administration application.
- Click Actions and select Schedule ETL.
- In the Schedule Frequency field, select the frequency for the ETL process run as Daily, Weekly or None.
If you select Daily:
- In the Run ETL at field, enter the start time for the daily ETL run and click Save.
- To schedule multiple ETL runs daily, click Add and enter a date and time for each ETL run.
If you select Weekly:
- In the Run ETL at field, enter the time for the process run.
- Select the days for running the RETL process, and click Save.
If you select None, the ETL process run will not be scheduled for a data source.
Note: It is recommended to schedule the ETL runs once a day at a minimum.