Adding Project-Level UDFs for Burn Down Calculations
Only P6 EPPM projects can be manually included to take advantage of the Burn Down tables and functionality. This section describes how to create and configure the necessary P6 EPPM project level user-defined fields (UDFs) that the STARETL process needs to include project(s) in Burn Down.
To create the project UDFs:
- Sign in to P6 EPPM with a user account that has the privilege to change enterprise data (for example, admin).
- From the Administration menu, select Enterprise Data.
- On the Enterprise Data page, expand Projects and select Project UDFs.
- On the Project UDFs page:
- Click + Add to add a sys_workdown UDF with a Text data type.
- Click + Add to add a sys_workdown_date UDF with a Start Date data type.