Adding Project UDFs for Work Planning

You can manually include P6 EPPM projects to take advantage of the Work Planning tables and functionality.

You must create and configure the necessary P6 EPPM project-level user-defined fields (UDFs) that the STARETL process needs to include projects in Work Planning.

To add project UDFs:

  1. Sign in to P6 EPPM.
  2. From the Administration menu, select Enterprise Data.
  3. On the Enterprise Data page, expand Projects and select Project UDFs.
  4. On the Project UDFs page:
    1. Add a sys_workprocess UDF with a data type of Text.
    2. Add a sys_scope_freeze UDF with a data type of Text.
    3. Add a sys_schedule_freeze UDF with a data type of Text.

Related Topics

Configuring Projects for Work Planning Calculations and Metrics

Selecting Projects for Work Planning Calculations