Using Graded Approach for Schedule Adherence

Graded approach to schedule adherence is a method for tracking adherence using four distinct levels of work scheduling (A, B, C, and D).

The levels of work scheduling are:

For graded schedule adherence, ensure history exists for the project as of the scheduled freeze date and T-0 baseline date for the week the STARETL process will run.

During T-0 for a given week when you run the STARETL process, the Baseline Planned Finish Date (as of T-0) and the Schedule Freeze Planned Finish Date (as of schedule freeze UDF) for the activities will be captured. You can use these dates along with the assigned adherence grade to calculate the graded schedule adherence in CIC Analytics.

To configure graded schedule adherence:

  1. Ensure you have enabled a project for Work Process.

    The sys_workprocess=WORKWEEK, sys_scope_freeze, and sys_schedule_freeze UDFs are populated and History Level is set to Activity.

  2. Ensure history exists for the project as of the scheduled freeze date and T-0 baseline date for the week the STARETL process will run in CIC Analytics.
  3. Code activities using an Activity Code or UDF to identify the adherence grade (A, B, C, D).

    For example, in the sample data, Activity Code 11 (Schedule Adherence Priority) is used.

Related Topics

Configuring P6 EPPM Projects for CIC

Configuring User Access for P6 Analytics Module

Selecting P6 Projects for CIC for the First Time

Enabling History and Publication Services Settings for P6 Projects

Enabling Slowly Changing Dimensions for P6 Projects

Adding Additional Financial Periods

Configuring P6 EPPM Projects for Burn Down Calculations

Configuring Projects for Work Planning Calculations and Metrics

Enabling P6 Location Data for Mapping



Last Published Friday, December 8, 2023