P6 - Project History / Primavera - Project History

Description: Use this subject area to analyze project and WBS-level history, including changes to both facts and dimensions, to better understand changes over time. This subject area requires project-specific configuration in P6.

Folder

Subfolder

Field Name

Dimension/ Fact / Lookup

Description

Values Derived From / Calculated By

Fact - Primavera - Project History

Period Cost

Next This Period Expense Cost

Fact

The Expense Cost planned in the next period

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.NEXT_PER_EXPENSE_COST_P

Fact - Primavera - Project History

Period Cost

Next This Period Labor Cost

Fact

The Labor Cost planned for the next period

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.NEXT_PER_LABOR_COST_P

Fact - Primavera - Project History

Period Cost

Next This Period Material Cost

Fact

The Material Cost planned in the next period

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.NEXT_PER_MATERIAL_COST_P

Fact - Primavera - Project History

Period Cost

Next This Period Nonlabor Cost

Fact

The Nonlabor Cost planned in the next period

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.NEXT_PER_NONLABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Actual Cost

Fact

The Actual Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.ACTUAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Actual Expense Cost

Fact

The Actual Expense Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.ACTUAL_EXPENSE_COST_P

Fact - Primavera - Project History

Period Cost

Period Actual Labor Cost

Fact

The Actual Labor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.ACTUAL_LABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Actual Material Cost

Fact

The Actual Material Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.ACTUAL_MATERIAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Actual Nonlabor Cost

Fact

The Actual Nonlabor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.ACTUAL_NONLABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Actual Total Cost

Fact

The Actual Total Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.ACTUAL_TOTAL_COST_P

Fact - Primavera - Project History

Period Cost

Period At Completion Expense Cost

Fact

The At Completion Expense Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.AT_COMPLETION_EXPENSE_COST_P

Fact - Primavera - Project History

Period Cost

Period At Completion Labor Cost

Fact

The At Completion Labor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.AT_COMPLETION_LABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period At Completion Material Cost

Fact

The At Completion Material Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.AT_COMPLETION_MATERIAL_COST_P

Fact - Primavera - Project History

Period Cost

Period At Completion Nonlabor Cost

Fact

The At Completion Nonlabor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.AT_COMPLETION_NONLABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period At Completion Total Cost

Fact

The At Completion Total Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.AT_COMPLETION_TOTAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Baseline Actual Expense Cost

Fact

The Baseline Actual Expense Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_ACTUAL_EXPENSE_COST_P

Fact - Primavera - Project History

Period Cost

Period Baseline Actual Labor Cost

Fact

The Baseline Actual Labor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_ACTUAL_LABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Baseline Actual Material Cost

Fact

The Baseline Actual Material Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_ACTUAL_MATERIAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Baseline Actual Nonlabor Cost

Fact

The Baseline Actual Nonlabor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_ACTUAL_NONLABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Baseline Actual Total Cost

Fact

The Baseline Actual Total Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_ACTUAL_TOTAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Baseline Project Expense Cost

Fact

The Baseline Project Expense Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_PLANNED_EXPENSE_COST_P

Fact - Primavera - Project History

Period Cost

Period Baseline Project Labor Cost

Fact

The Baseline Project Labor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_PLANNED_LABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Baseline Project Material Cost

Fact

The Baseline Project Material Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_PLANNED_MATERIAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Baseline Project Nonlabor Cost

Fact

The Baseline Project Nonlabor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_PLANNED_NONLABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Baseline Project Total Cost

Fact

The Baseline Project Total Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_PLANNED_TOTAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Earned Value Cost

Fact

The Earned Value Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.EARNED_VALUE_COST_P

Fact - Primavera - Project History

Period Cost

Period Estimate At Completion Cost

Fact

The Estimate at Completion Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.EST_AT_COMPLETION_COST_P

Fact - Primavera - Project History

Period Cost

Period Estimate To Completion Cost

Fact

The Estimate To Completion Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.EST_TO_COMPLETE_COST_P

Fact - Primavera - Project History

Period Cost

Period Planned Expense Cost

Fact

The Planned Expense Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PLANNED_EXPENSE_COST_P

Fact - Primavera - Project History

Period Cost

Period Planned Labor Cost

Fact

The Planned Labor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PLANNED_LABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Planned Material Cost

Fact

The Planned Material Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PLANNED_MATERIAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Planned Nonlabor Cost

Fact

The Planned Nonlabor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PLANNED_NONLABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Planned Total Cost

Fact

The Planned Total Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PLANNED_TOTAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Planned Value Cost

Fact

The Planned Value Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PLANNED_VALUE_COST_P

Fact - Primavera - Project History

Period Cost

Period Remaining Expense Cost

Fact

The Remaining Expense Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_EXPENSE_COST_P

Fact - Primavera - Project History

Period Cost

Period Remaining Labor Cost

Fact

The Remaining Labor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Remaining Late Expense Cost

Fact

The Remaining Late Expense Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LATE_EXPENSE_COST_P

Fact - Primavera - Project History

Period Cost

Period Remaining Late Labor Cost

Fact

The Remaining Late Labor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LATE_LABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Remaining Late Material Cost

Fact

The Remaining Late Material Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LATE_MATERIAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Remaining Late Nonlabor Cost

Fact

The Remaining Late Nonlabor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LATE_NONLABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Remaining Late Total Cost

Fact

The Remaining Late Total Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LATE_TOTAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Remaining Material Cost

Fact

The Remaining Material Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_MATERIAL_COST_P

Fact - Primavera - Project History

Period Cost

Period Remaining Nonlabor Cost

Fact

The Remaining Nonlabor Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_NONLABOR_COST_P

Fact - Primavera - Project History

Period Cost

Period Remaining Total Cost

Fact

The Remaining Total Cost for the period specified

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_TOTAL_COST_P

Fact - Primavera - Project History

Period Cost

Previous This Period Expense Cost

Fact

The Expense Cost planned in the previous period

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PREV_THIS_PER_EXPENSE_COST

Fact - Primavera - Project History

Period Cost

Previous This Period Labor Cost

Fact

The Period Labor Cost planned in the previous period

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PREV_THIS_PER_LABOR_COST

Fact - Primavera - Project History

Period Cost

Previous This Period Material Cost

Fact

The Material Cost planned in the previous period

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PREV_THIS_PER_MATERIAL_COST

Fact - Primavera - Project History

Period Cost

Previous This Period Nonlabor Cost

Fact

The Nonlabor Cost planned in the previous period

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PREV_THIS_PER_NONLABOR_COST

Fact - Primavera - Project History

Costs

Actual Expense Cost

Fact

The actual cost for all project expenses associated with the activity.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.ACTUAL_EXPENSE_COST

Fact - Primavera - Project History

Costs

Actual Labor Cost

Fact

The actual cost for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Actual Labor Units * Project Default Price / Time.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.ACTUAL_LABOR_COST

Fact - Primavera - Project History

Costs

Actual Material Cost

Fact

The actual cost for all material resources assigned to the activity.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.ACTUAL_MATERIAL_COST

Fact - Primavera - Project History

Costs

Actual NonLabor Cost

Fact

The actual cost for all nonlabor resources assigned to the activity. If no resources are assigned, computed as the activity Actual Nonlabor Units * Project Default Price / Time.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.ACTUAL_NONLABOR_COST

Fact - Primavera - Project History

Costs

Actual Total Cost

Fact

The Actual Total Cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Actual Total Cost = Actual Labor Cost + Actual Nonlabor Cost + Actual Material Cost + Actual Expense Cost.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.ACTUAL_TOTAL_COST

Fact - Primavera - Project History

Costs

At Completion Expense Cost

Fact

The expense cost at completion is the sum of the actual plus remaining cost for all expenses associated with the activity. Computed as Actual Expense Cost + Remaining Expense Cost.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.AT_COMPLETION_EXPENSE_COST

Fact - Primavera - Project History

Costs

At Completion Labor Cost

Fact

The labor cost at completion is the sum of the actual plus remaining cost for all labor resources assigned to the activity. Computed as Actual Labor Cost + Remaining Labor Cost. Same as the budgeted labor cost if the activity is not started and the actual labor cost once the activity is completed.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.AT_COMPLETION_LABOR_COST

Fact - Primavera - Project History

Costs

At Completion Material Cost

Fact

The material cost at completion is the sum of the actual plus remaining cost for all material resources assigned to the activity. Computed as Actual Material Cost + Remaining Material Cost. Same as the budgeted material cost if the activity is not started and the actual material cost once the activity is completed.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.AT_COMPLETION_MATERIAL_COST

Fact - Primavera - Project History

Costs

At Completion Nonlabor Cost

Fact

The nonlabor cost at completion is the sum of the actual plus remaining cost for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Cost + Remaining Nonlabor Cost. Same as the budgeted nonlabor cost if the activity is not started and the actual nonlabor cost once the activity is completed.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.AT_COMPLETION_NONLABOR_COST

Fact - Primavera - Project History

Costs

At Completion Total Cost

Fact

The total cost at completion for the activity, including labor resources, nonlabor resources, material resources, and project expenses. At Completion Total Cost = At Completion Labor Cost + At Completion Nonlabor Cost + At Completion Material Cost + At Completion Expense Cost.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.AT_COMPLETION_TOTAL_COST

Fact - Primavera - Project History

Costs

Baseline Actual Nonlabor Cost

Fact

The actual cost for all the Nonlabor resources assigned to an activity in the project baseline

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_ACTUAL_NONLABOR_COST

Fact - Primavera - Project History

Costs

Baseline Actual Expense Cost

Fact

The actual cost for all the actual expenses associated with the activity in the project baseline.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_ACTUAL_EXPENSE_COST

Fact - Primavera - Project History

Costs

Baseline Actual Labor Cost

Fact

The actual cost for all the labor resources assigned to an activity in the project baseline.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_ACTUAL_LABOR_COST

Fact - Primavera - Project History

Costs

Baseline Actual Material Cost

Fact

The actual cost for all material resources assigned to the activity in the project baseline.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_ACTUAL_MATERIAL_COST

Fact - Primavera - Project History

Costs

Baseline Actual Total Cost

Fact

The actual total cost of the activity in the project baseline, including labor resources, non-labor resources, material resources, and project expenses.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_ACTUAL_TOTAL_COST

Fact - Primavera - Project History

Costs

Baseline Project Expense Cost

Fact

The cost for all the project expenses associated with the activity in the project baseline.

Value Derived From : Fact_W_WBS_HISTORY_F_Wbs_History.BL_PLANNED_EXPENSE_COST

Fact - Primavera - Project History

Costs

Baseline Project Labor Cost

Fact

The cost for all the labor resources assigned to an activity in the project baseline.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_PLANNED_LABOR_COST

Fact - Primavera - Project History

Costs

Baseline Project Material Cost

Fact

Budgeted or (At Completion)cost for all material resources assigned to the activity in the project baseline.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_PLANNED_MATERIAL_COST

Fact - Primavera - Project History

Costs

Baseline Project Nonlabor Cost

Fact

The cost for all the Nonlabor resources assigned to an activity in the project baseline

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_PLANNED_NONLABOR_COST

Fact - Primavera - Project History

Costs

Baseline Project Total Cost

Fact

The total cost of the activity in the project baseline, including labor resources, non-labor resources, material resources, and project expenses.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.BL_PLANNED_TOTAL_COST

Fact - Primavera - Project History

Costs

Planned Expense Cost

Fact

Planned Expense Cost

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PLANNED_EXPENSE_COST

Fact - Primavera - Project History

Costs

Planned Labor Cost

Fact

The budgeted costs for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Budgeted Labor Units * Project Default Price / Time.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PLANNED_LABOR_COST

Fact - Primavera - Project History

Costs

Planned Material Cost

Fact

The budgeted costs for all material resources assigned to the activity. If no resources are assigned, computed as the activity Budgeted Labor Units * Project Default Price / Time.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PLANNED_MATERIAL_COST

Fact - Primavera - Project History

Costs

Planned Nonlabor Cost

Fact

The budgeted costs for all nonlabor resources assigned to the activity.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PLANNED_NONLABOR_COST

Fact - Primavera - Project History

Costs

Planned Total Cost

Fact

The budgeted total cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Budgeted Total Cost = Budgeted Labor Cost + Budgeted Nonlabor Cost + Budgeted Material Cost + Budgeted Expense Cost.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.PLANNED_TOTAL_COST

Fact - Primavera - Project History

Costs

Remaining Expense Cost

Fact

The remaining cost for all project expenses associated with the activity.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_EXPENSE_COST

Fact - Primavera - Project History

Costs

Remaining Labor Cost

Fact

The remaining cost for all labor resources assigned to the activity. If no resources are assigned, computed as the activity Remaining Labor Units * Project Default Price / Time.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LABOR_COST

Fact - Primavera - Project History

Costs

Remaining Late Expense Cost

Fact

Remaining Late Expense Cost

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LATE_EXPENSE_COST

Fact - Primavera - Project History

Costs

Remaining Late Labor Cost

Fact

Remaining Late Labor Cost

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LATE_LABOR_COST

Fact - Primavera - Project History

Costs

Remaining Late Material Cost

Fact

Remaining Late Material Cost

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LATE_MATERIAL_COST

Fact - Primavera - Project History

Costs

Remaining Late Nonlabor Cost

Fact

Remaining Late Nonlabor Cost

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LATE_NONLABOR_COST

Fact - Primavera - Project History

Costs

Remaining Late Total Cost

Fact

Remaining Late Total Cost

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_LATE_TOTAL_COST

Fact - Primavera - Project History

Costs

Remaining Material Cost

Fact

The remaining cost for all material resources assigned to the activity.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_MATERIAL_COST

Fact - Primavera - Project History

Costs

Remaining Nonlabor Cost

Fact

The remaining cost for all nonlabor resources assigned to the activity. If no resources are assigned, computed as the activity Remaining Nonlabor Units * Project Default Price / Time.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_NONLABOR_COST

Fact - Primavera - Project History

Costs

Remaining Total Cost

Fact

The remaining total cost for the activity, including labor resources, nonlabor resources, material resources, and project expenses. Remaining Total Cost = Remaining Labor Cost + Remaining Nonlabor Cost + Remaining Material Cost + Remaining Expense Cost.

Value Derived From : Fact_W_PROJECT_HISTORY_F_Project_History.REMAINING_TOTAL_COST

Fact - Primavera - Project History

Dates

 

 

Dates

 

Fact - Primavera - Project History

Dates

Actual Finish

Fact

The date on which the activity actually finished

last(max(Fact_W_WBS_HISTORY_F_Wbs_History.ACTUAL_FINISH_DATE))

Fact - Primavera - Project History

Dates

Actual Start

Fact

The date on which the activity actually started

last(min(Fact_W_WBS_HISTORY_F_Wbs_History.ACTUAL_START_DATE))

Fact - Primavera - Project History

Dates

Baseline Project Finish

Fact

The Project Baseline Planned Finish Date.

last(max(Fact_W_WBS_HISTORY_F_Wbs_History.BASELINE_FINISH_DATE))

Fact - Primavera - Project History

Dates

Baseline Project Start

Fact

The Project Baseline Planned Start Date.

last(min(Fact_W_WBS_HISTORY_F_Wbs_History.BASELINE_START_DATE))

Fact - Primavera - Project History

Dates

Finish

Fact

The current finish date of the activity. Set to the activity remaining early finish date while the activity is not started or in progress, and the actual finish date once the activity is completed.

last(max(Fact_W_WBS_HISTORY_F_Wbs_History.FINISH_DATE))

Fact - Primavera - Project History

Dates

Planned Finish

Fact

The date the activity is scheduled to finish. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started.

last(min(Fact_W_WBS_HISTORY_F_Wbs_History.START_DATE))

Fact - Primavera - Project History

Dates

Planned Start

Fact

The date the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started.

last(min(Fact_W_WBS_HISTORY_F_Wbs_History.PLANNED_START_DATE))

Fact - Primavera - Project History

Dates

Remaining Finish

Fact

Remaining Finish

last(max(Fact_W_WBS_HISTORY_F_Wbs_History.REMAINING_FINISH_DATE))

Fact - Primavera - Project History

Dates

Remaining Start

Fact

Remaining Start

last(min(Fact_W_WBS_HISTORY_F_Wbs_History.REMAINING_START_DATE))

Fact - Primavera - Project History

Dates

Start

Fact

The current start date of the activity. Set to the activity remaining early start date while the activity is not started, and the actual start date once the activity is started.

last(min(Fact_W_WBS_HISTORY_F_Wbs_History.START_DATE))

Fact - Primavera - Project History

Durations

 

 

Durations

 

Fact - Primavera - Project History

Durations

Actual Duration

Fact

Actual duration is the total working time from the activity actual start date to the actual finish date (for completed activities), or to the current data date (for in-progress activities). The actual working time is computed using the activity's calendar.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.ACTUAL_DURATION))

Fact - Primavera - Project History

Durations

At Completion Duration

Fact

The duration at completion is the total working time from the activity's current start date to the current finish date. The current start date is the planned start date until the activity is started, then it is the actual start date. The current finish date is the activity planned finish date while the activity is not started, the remaining finish date while the activity is in progress, and the actual finish date once the activity is completed. The total working time is computed using the activity's calendar.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.AT_COMPLETION_DURATION))

Fact - Primavera - Project History

Durations

Baseline Project Duration

Fact

The duration for the activity in the primary baseline.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.BASELINE_DURATION))

Fact - Primavera - Project History

Durations

Variance - Baseline Project Duration

Fact

Variance duration is the duration between the activity' Baseline project duration and the At Completion duration.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.DURATION_VARIANCE))

Fact - Primavera - Project History

Durations

Planned Duration

Fact

Planned Duration is the planned working time for the resource assignment on the activity, from the resource's planned start date to the planned finish date. The planned working time is computed using the calendar determined by the Activity Type. Resource Dependent activities use the resource's calendar; other activity types use the activity's calendar. This is the duration that Progress Reporter users follow and the schedule variance is measured against.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PLANNED_DURATION))

Fact - Primavera - Project History

Durations

Remaining Duration

Fact

Remaining duration is the total working time from the activity remaining start date to the remaining finish date. The remaining working time is computed using the activity's calendar. Before the activity is started, the remaining duration is the same as the Original Duration. After the activity is completed the remaining duration is zero.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.REMAINING_DURATION))

Fact - Primavera - Project History

Durations

Total Float

Fact

The amount of time the activity can be delayed before delaying the project finish date. Total float can be computed as Late Start - Early Start or as Late Finish - Early Finish; this option can be set when running the project scheduler.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.TOTAL_FLOAT))

Fact - Primavera - Project History

Earned Value - (Cost)

 

 

Earned Value (Cost)

 

Fact - Primavera - Project History

Earned Value - (Cost)

Accounting Variance (Cost)

Fact

Accounting Variance is the Planned Value minus the Actual Cost. A negative value indicates that Actual Cost have exceeded the Planned Value

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.EARNED_VALUE_COST))

Fact - Primavera - Project History

Earned Value - (Cost)

Cost Performance Index (Cost)

Fact

Cost Performance Index is the Earned Value divided by the Actual Cost. A value less than 1 indicates that Actual Cost have exceeded the Planned Value.

P6Core."Fact - Project History"."Earned Value Cost" / ( IFNULL("P6Core"."Fact - Project History"."Actual Cost", 0))

Fact - Primavera - Project History

Earned Value - (Cost)

Cost Schedule Index (Cost)

Fact

Cost Schedule Index By Cost

P6Core."Fact - Project History"."Earned Value Cost" / ( IFNULL("P6Core"."Fact - Project History"."Actual Cost", 0)) * ( IFNULL("P6Core"."Fact - Project History"."Earned Value Cost", 0)) / ( IFNULL("P6Core"."Fact - Project History"."Planned Value Cost", 0))

Fact - Primavera - Project History

Earned Value - (Cost)

Cost Variance (Cost)

Fact

Cost Variance is the Earned Value minus the Actual Cost. A negative value indicates that Actual Cost have exceeded the Planned Value.

P6Core."Fact - Project History"."Earned Value Cost" - "P6Core"."Fact - Project History"."Actual Cost"

Fact - Primavera - Project History

Earned Value - (Cost)

Cost Variance Index (Cost)

Fact

Cost Variance Index is the Cost Variance divided by Earned Value.

P6Core."Fact - Project History"."Cost Variance" / "P6Core"."Fact - Project History"."Earned Value Cost"

Fact - Primavera - Project History

Earned Value - (Cost)

Earned Value (Cost)

Fact

Earned value cost for the project

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.EARNED_VALUE_COST))

Fact - Primavera - Project History

Earned Value - (Cost)

Estimate At Completion (Cost)

Fact

Estimate Cost at Completion is the Actual Cost plus the Estimate to Complete Cost. The method for computing Estimate to Complete depends on the Earned Value technique selected for the activity's WBS.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.EST_AT_COMPLETION_COST))

Fact - Primavera - Project History

Earned Value - (Cost)

Estimate to Complete (Cost)

Fact

Calculated Estimate To Complete using specified technique

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.EST_TO_COMPLETE_COST))

Fact - Primavera - Project History

Earned Value - (Cost)

Planned Value (Cost)

Fact

Planned cost of work scheduled for the project

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PLANNED_VALUE_COST))

Fact - Primavera - Project History

Earned Value - (Cost)

Schedule Performance Index (Cost)

Fact

Schedule Performance Index is the Earned Value divided by Planned Value. A value less than 1 indicates that less work was actually performed than was scheduled.

P6Core."Fact - Project History"."Earned Value Cost" / "P6Core"."Fact - Project History"."Planned Value Cost"

Fact - Primavera - Project History

Earned Value - (Cost)

Schedule Variance (Cost)

Fact

Schedule Variance is the Earned Value minus the Planned Value. A negative value indicates that less work was actually performed than was scheduled.

P6Core."Fact - Project History"."Earned Value Cost" - "P6Core"."Fact - Project History"."Planned Value Cost"

Fact - Primavera - Project History

Earned Value - (Cost)

Schedule Variance Index (Cost)

Fact

Schedule Variance Index is the Schedule Variance divided by Planned Value.

P6Core."Fact - Project History"."Schedule Variance Cost" / "P6Core"."Fact - Project History"."Planned Value Cost"

Fact - Primavera - Project History

Earned Value - (Cost)

To Complete Performance Index - BAC (Cost)

Fact

To Complete Performance Index - BAC (Cost)

("P6Core"."Fact - Project History"."Bl Planned Total Cost" - "P6Core"."Fact - Project History"."Earned Value Cost") / (IFNULL("P6Core"."Fact - Project History"."Bl Planned Total Cost" - "P6Core"."Fact - Project History"."Actual Cost", 0))

Fact - Primavera - Project History

Earned Value - (Cost)

To Complete Performance Index - EAC (Cost)

Fact

To Complete Performance Index - EAC (Cost)

("P6Core"."Fact - Project History"."Bl Planned Total Cost" - "P6Core"."Fact - Project History"."Earned Value Cost") / ((IFNULL("P6Core"."Fact - Project History"."Est At Completion Cost",0)) - (IFNULL("P6Core"."Fact - Project History"."Actual Cost",0)))

Fact - Primavera - Project History

Earned Value - (Cost)

Variance At Completion (Cost)

Fact

Variance At Completion is the Budget At Completion (baseline total cost) minus Estimate At Completion.

P6Core."Fact - Project History"."Bl Planned Total Cost" - "P6Core"."Fact - Project History"."Est At Completion Cost"

Fact - Primavera - Project History

Earned Value - (Units)

 

 

Earned Value (Units)

 

Fact - Primavera - Project History

Earned Value - (Units)

Accounting Variance (Units)

Fact

Accounting Variance Labor Units is the Planned Value Labor Units minus the Actual Units. Negative value indicates that Actual Units have exceeded the Planned Value Labor Units.

P6Core."Fact - Project History"."Planned Value Labor Units" - "P6Core"."Fact - Project History"."Actual Labor Units"

Fact - Primavera - Project History

Earned Value - (Units)

Budget At Completion (Units)

Fact

Budget at Completion Labor Units is the baseline Labor Units + baseline Nonlabor Labor Units + baseline Expense Labor Units + baseline Material Labor Units. Same as the baseline Total Labor Units.

P6Core."Fact - Project History"."Baseline Project Labor Units"

Fact - Primavera - Project History

Earned Value - (Units)

Cost Performance Index (Units)

Fact

Cost Performance Index Labor Units is the Earned Value Labor Units / Actual Labor Units.

P6Core."Fact - Project History"."Earned Value Labor Units" / "P6Core"."Fact - Project History"."Actual Labor Units"

Fact - Primavera - Project History

Earned Value - (Units)

Cost Schedule Index (Units)

Fact

Cost Schedule Index By Units

P6Core."Fact - Project History"."Cost Performance Index (CPI) - Labor Units" * "P6Core"."Fact - Project History"."Schedule Performance Index (SPI) Labor Units"

Fact - Primavera - Project History

Earned Value - (Units)

Cost Variance (Units)

Fact

Cost Variance Labor Units is Earned Value Labor Units minus Actual Labor Units.

P6Core."Fact - Project History"."Earned Value Labor Units" - "P6Core"."Fact - Project History"."Actual Labor Units"

Fact - Primavera - Project History

Earned Value - (Units)

Cost Variance Index (Units)

Fact

Cost Variance Index is the Cost Variance divided by Earned Value.

("P6Core"."Fact - Project History"."Earned Value Labor Units" - "P6Core"."Fact - Project History"."Actual Labor Units") / "P6Core"."Fact - Project History"."Earned Value Labor Units"

Fact - Primavera - Project History

Earned Value - (Units)

Earned Value (Units)

Fact

Earned Value Labor Units Performed is the portion of the baseline Labor Units that is actually completed as of the project data date. Computed as baseline Labor Units * Performance % Complete. The Earned Value Labor Units is essentially the labor units earned value for the activity. The method for computing the Performance % Complete depends on the earned value technique selected for the activity's WBS. The baseline Labor Units is taken from the baseline.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.EARNED_VALUE_LABOR_UNITS))

Fact - Primavera - Project History

Earned Value - (Units)

Estimate At Completion (Units)

Fact

Estimate At Completion Labor Units is calculated as Actual Labor Units + Estimate To Complete Labor Units. (Estimate To Complete Labor Units is calculated based off of the Earned Value setting on the WBS.)

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.EST_AT_COMPLETION_LABOR_UNITS))

Fact - Primavera - Project History

Earned Value - (Units)

Estimate To Complete (Units)

Fact

The estimated quantity to complete of the activity. Computed as either the remaining total units for the activity, or as Performance Factor * (Baseline Budgeted Labor Units - Budgeted Quantity of Work Performed), depending on the Earned Value Technique selected for the activity's WBS.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.EST_TO_COMPLETE_LABOR_UNITS))

Fact - Primavera - Project History

Earned Value - (Units)

Variance - Baseline Project Finish Date

Fact

Variance Finish Date is the duration between the Baseline project finish date and the finish date in the current project.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.FINISH_DATE_VARIANCE))

Fact - Primavera - Project History

Earned Value - (Units)

Planned Value (Units)

Fact

Planned Value Labor Units Scheduled is the portion of the baseline Labor Units that is scheduled to be completed as of the project data date. For activities without resource assignments, and for activity resource assignments that do not have resource curves, computed as baseline Labor Units * Schedule % Complete. For activity resource assignments that do have resource curves, the curve distribution is additionally factored into the calculation. The Schedule % Complete specifies how much of the activity's baseline duration has been completed so far. The baseline Labor Units is taken from the baseline.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PLANNED_VALUE_LABOR_UNITS))

Fact - Primavera - Project History

Earned Value - (Units)

Planned Value Nonlabor (Units)

Fact

Planned Value Nonlabor (Units)

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.BL_PLANNED_NONLABOR_UNITS))

Fact - Primavera - Project History

Earned Value - (Units)

Schedule Performance Index (Units)

Fact

Schedule Performance Index Labor Units is the Earned Value Labor Units divided by Planned Value Labor Units.

P6Core."Fact - Project History"."Earned Value Labor Units" / "P6Core"."Fact - Project History"."Planned Value Labor Units"

Fact - Primavera - Project History

Earned Value - (Units)

Schedule Variance (Units)

Fact

Schedule Variance Labor Units is the Earned Value Labor Units minus Planned Value Labor Units.

P6Core."Fact - Project History"."Earned Value Labor Units" - "P6Core"."Fact - Project History"."Planned Value Labor Units"

Fact - Primavera - Project History

Earned Value - (Units)

Schedule Variance Index (Units)

Fact

Schedule Variance Index is the Schedule Variance Labor Units divided by the Planned Value Labor Units.

P6Core."Fact - Project History"."Schedule Variance Labor Units" / "P6Core"."Fact - Project History"."Planned Value Labor Units"

Fact - Primavera - Project History

Earned Value - (Units)

Variance - Baseline Project Start Date

Fact

Variance Start Date is the duration between the Baseline project start date and the start date in the current project.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.START_DATE_VARIANCE))

Fact - Primavera - Project History

Earned Value - (Units)

To Complete Performance Index - BAC (Units)

Fact

The To Complete Performance Index is (Budget at Completion (BAC) - Earned Value Labor Units) / (Budget at Completion (BAC) - Actual Labor Units).

("P6Core"."Fact - Project History"."Budget At Completion (BAC) - Labor Units" - "P6Core"."Fact - Project History"."Earned Value Labor Units") / ("P6Core"."Fact - Project History"."Budget At Completion (BAC) - Labor Units" - "P6Core"."Fact - Project History"."Actual Labor Units")

Fact - Primavera - Project History

Earned Value - (Units)

To Complete Performance Index - EAC (Units)

Fact

The To Complete Performance Index is (Budget at Completion (EAC) - Earned Value Labor Units) / (Estimated at Completion - Actual Labor Units).

("P6Core"."Fact - Project History"."Budget At Completion (BAC) - Labor Units" - "P6Core"."Fact - Project History"."Earned Value Labor Units") / ("P6Core"."Fact - Project History"."Estimate At Completion Labor Units" - "P6Core"."Fact - Project History"."Actual Labor Units")

Fact - Primavera - Project History

Metrics

 

 

Metrics

 

Fact - Primavera - Project History

Metrics

# Of Activities

Fact

# Of Activities

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.TOTAL_ACTIVITY_COUNT))

Fact - Primavera - Project History

Metrics

# Of Completed Activities

Fact

The number of activities that were Completed during the specific Project History Interval.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.COMPLETED_ACTIVITY_COUNT))

Fact - Primavera - Project History

Metrics

# Of In Progress Activities

Fact

The number of activities that are InProgress during the specific Project History Interval.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.IN_PROGRESS_ACTIVITY_COUNT))

Fact - Primavera - Project History

Metrics

# Of Not Started Activities

Fact

The number of activities that are Not Started during the specific Project History Interval.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.NOT_STARTED_ACTIVITY_COUNT))

Fact - Primavera - Project History

Metrics

# Of Projects

Fact

# Of Projects

last(count(distinct Fact_W_WBS_HISTORY_F_Wbs_History.PROJECT_WID))

Fact - Primavera - Project History

Metrics

Completed Last Period

Fact

Activities with Completed status at the time of the previous ETL run

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.COMPLETED_THIS_PERIOD))

Fact - Primavera - Project History

Metrics

Completed This Period

Fact

Activities whose actual finish date fell between the period start and period end for this ETL run

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.COMPLETED_LAST_PERIOD))

Fact - Primavera - Project History

Metrics

Delayed This Period

Fact

Activities planned to start between the period start and period end with no actual start date

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.DELAYED_THIS_PERIOD))

Fact - Primavera - Project History

Metrics

Emergent Count

Fact

Activities added before the period start date of this ETL run

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.EMERGENT_WORK))

Fact - Primavera - Project History

Metrics

In Progress Last Period

Fact

Activities with In Progress status at the time of the previous ETL run

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.IN_PROGRESS_LAST_PERIOD))

Fact - Primavera - Project History

Metrics

In Progress This Period

Fact

Activities whose actual start date fell between the period start and period end for this ETL run

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.IN_PROGRESS_THIS_PERIOD))

Fact - Primavera - Project History

Metrics

Not Started Last Period

Fact

Activities with Not Started status at the time of the previous ETL run

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.NOT_STARTED_LAST_PERIOD))

Fact - Primavera - Project History

Metrics

Risk Exposure

Fact

The calculated exposure value for the risk

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PROJECT_RISK_EXPOSURE))

Fact - Primavera - Project History

Metrics

Risk Score

Fact

The calculated score value of the impact values assigned to the risk

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PROJECT_RISK_SCORE))

Fact - Primavera - Project History

Percent Completes

 

 

Percent Completes

 

Fact - Primavera - Project History

Percent Completes

Cost % Complete

Fact

The percent complete of cost for all labor resources, nonlabor resources, material resources, and expenses for the activity. Computed as Actual Total Cost / At Completion Total Cost * 100. Always in the range 0 to 100.

P6Core."Fact - Project History"."Actual Total Cost" / P6Core."Fact - Project History"."At Completion Total Cost" * 100

Fact - Primavera - Project History

Percent Completes

Duration % Complete

Fact

The percent complete of the activity duration. Computed as (Original Duration - Remaining Duration)/Original Duration * 100. Always in the range 0 to 100. The Original Duration is taken from the current plan, not from the baseline.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.DURATION_PCT_COMPLETE))

Fact - Primavera - Project History

Percent Completes

Duration % Of Planned

Fact

The percent complete of the activity duration. Computed as (Planned Duration - Remaining Duration)/Original Duration * 100. Always in the range 0 to 100. The Planned Duration is taken from the current plan, not from the baseline.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.DURATION_PCT_OF_PLANNED))

Fact - Primavera - Project History

Percent Completes

Expense Cost % Complete

Fact

Percent complete of cost for all expenses associated with an activity. Computed as Actual Expense Cost / At Completion Expense Cost* 100. Always in the range 0 to 100.

P6Core."Fact - Project History"."Actual Expense Cost" / P6Core."Fact - Project History"."At Completion Expense Cost" * 100

Fact - Primavera - Project History

Percent Completes

Labor Cost % Complete

Fact

The percent complete of cost for all labor resources assigned to the activity. Computed as Actual Labor Cost / At Completion Labor Cost * 100. Always in the range 0 to 100.

P6Core."Fact - Project History"."Actual Labor Cost" / P6Core."Fact - Project History"."At Completion Labor Cost" * 100

Fact - Primavera - Project History

Percent Completes

Labor Units % Complete

Fact

The percent complete of units for all labor resources for the activity. Computed as Actual Labor Units / At Completion Labor Units * 100. Always in the range 0 to 100.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.LABOR_UNITS_PCT_COMPLETE))

Fact - Primavera - Project History

Percent Completes

Material Cost % Complete

Fact

The percent complete of cost for all material resources assigned to the activity. Computed as Actual Material Cost / At Completion Material Cost * 100. Always in the range 0 to 100.

P6Core."Fact - Project History"."Actual Material Cost" / P6Core."Fact - Project History"."At Completion Material Cost" * 100

Fact - Primavera - Project History

Percent Completes

Nonlabor Cost % Complete

Fact

The percent complete of cost for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Cost / At Completion Nonlabor Cost * 100. Always in the range 0 to 100.

P6Core."Fact - Project History"."Actual Nonlabor Cost" / P6Core."Fact - Project History"."At Completion Nonlabor Cost" * 100

Fact - Primavera - Project History

Percent Completes

Nonlabor Units % Complete

Fact

The percent complete of units for all nonlabor resources for the activity. Computed as Actual Nonlabor Units / At Completion Nonlabor Units * 100. Always in the range 0 to 100.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.NONLABOR_UNITS_PCT_COMPLETE))

Fact - Primavera - Project History

Percent Completes

Performance % Complete

Fact

The activity performance percent complete. The performance percent complete is used to compute earned value and may be based on the Activity % Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far.

P6Core."Fact - Project History"."Earned Value Cost" / P6Core."Fact - Project History"."Budget at Completion" * 100

Fact - Primavera - Project History

Percent Completes

Schedule % Complete

Fact

The activity schedule percent complete. The Schedule % Complete specifies how much of the activity's baseline duration has been completed so far. Computed based on where the current data date falls between the activity's baseline start and finish dates. If the data date is earlier than the baseline Start, the Schedule % Complete is 0. If the data date is later than the baseline Finish, the Schedule % Complete is 100. The Schedule % Complete indicates how much of the activity duration should be currently completed, relative to the selected baseline.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.SCHEDULE_PCT_COMPLETE))

Fact - Primavera - Project History

Percent Completes

Units % Complete

Fact

The percent complete of units for all labor and nonlabor resources assigned to the activity. Computed as Actual Units / At Completion Units * 100. Always in the range 0 to 100.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.UNITS_PCT_COMPLETE))

Fact - Primavera - Project History

Units

 

 

Units

 

Fact - Primavera - Project History

Units

Actual Labor Units

Fact

The actual units for all labor resources assigned to the activity.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.ACTUAL_LABOR_UNITS))

Fact - Primavera - Project History

Units

Actual Nonlabor Units

Fact

The actual units for all nonlabor resources assigned to the activity.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.ACTUAL_NONLABOR_UNITS))

Fact - Primavera - Project History

Units

At Completion Labor Units

Fact

The labor units at completion is the sum of the actual plus remaining units for all labor resources assigned to the activity. Computed as Actual Labor Units + Remaining Labor Units. Same as the budgeted labor units if the activity is not started and the actual labor units once the activity is completed.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.AT_COMPLETION_LABOR_UNITS))

Fact - Primavera - Project History

Units

At Completion Nonlabor Units

Fact

The nonlabor units at completion is the sum of the actual plus remaining units for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Units + Remaining Nonlabor Units. Same as the budgeted nonlabor units if the activity is not started and the actual nonlabor units once the activity is completed.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.AT_COMPLETION_NONLABOR_UNITS))

Fact - Primavera - Project History

Units

Baseline Actual Labor Units

Fact

The actual units for all labor resources assigned to the activity in the project baseline

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.BL_ACTUAL_LABOR_UNITS))

Fact - Primavera - Project History

Units

Baseline Actual Nonlabor Units

Fact

The actual units for all the Nonlabor resources assigned to an activity in the project baseline

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.BL_ACTUAL_NONLABOR_UNITS))

Fact - Primavera - Project History

Units

Baseline Project Labor Units

Fact

The units for all the labor resources assigned to an activity in the project baseline.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.BL_PLANNED_LABOR_UNITS))

Fact - Primavera - Project History

Units

Baseline Project Nonlabor Units

Fact

The units for all the Nonlabor resources assigned to an activity in the project baseline

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.BL_PLANNED_NONLABOR_UNITS))

Fact - Primavera - Project History

Period Units

Next This Period Labor Units

Fact

This Period Labor Units for the period after the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.NEXT_PER_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Next This Period Nonlabor Units

Fact

This Period Nonlabor Units for the period after the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.NEXT_PER_NONLABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Actual Labor Units

Fact

Period Actual Labor Units

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.ACTUAL_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Actual Nonlabor Units

Fact

The Actual Nonlabor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.ACTUAL_NONLABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period At Completion Labor Units

Fact

The At Completion Labor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.AT_COMPLETION_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Baseline Actual Labor Units

Fact

The Baseline Actual Labor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.BL_ACTUAL_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Baseline Actual Nonlabor Units

Fact

The Baseline Actual Nonlabor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.BL_ACTUAL_NONLABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Baseline Project Labor Units

Fact

The Baseline Project Labor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.BL_PLANNED_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Baseline Project Nonlabor Units

Fact

The Baseline Project Nonlabor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.BL_PLANNED_NONLABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Earned Value Labor Units

Fact

The Earned Value Labor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.EARNED_VALUE_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Estimate At Completion Labor Units

Fact

The Estimate At Completion Labor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.EST_AT_COMPL_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Estimate To Completion Labor Units

Fact

The Estimate to Completion Labor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.EST_TO_COMPLETE_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Planned Labor Units

Fact

Period Planned Labor Units

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PLANNED_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Planned Nonlabor Units

Fact

The Planned Nonlabor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PLANNED_NONLABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Planned Value Labor Units

Fact

The Planned Value Labor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PLANNED_VALUE_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Remaining Labor Units

Fact

The Remaining Labor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.REMAINING_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Remaining Late Labor Units

Fact

The Remaining Late Labor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.REMAINING_LATE_LABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Remaining Late Nonlabor Units

Fact

The Remaining Late Nonlabor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.REM_LATE_NONLABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period Remaining Nonlabor Units

Fact

The Remaining Nonlabor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.REMAINING_NONLABOR_UNITS_P))

Fact - Primavera - Project History

Period Units

Period At Completion Nonlabor Units

Fact

The At Completion Nonlabor Units for the period specified

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.AT_COMPLETION_NONLABOR_UNITS_P))

Fact - Primavera - Project History

Units

Planned Labor Units

Fact

The budgeted units for all labor resources assigned to the activity.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PLANNED_LABOR_UNITS))

Fact - Primavera - Project History

Units

Planned Nonlabor Units

Fact

The budgeted units for all nonlabor resources assigned to the activity.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PLANNED_NONLABOR_UNITS))

Fact - Primavera - Project History

Period Units

Previous This Period Labor Units

Fact

Previous This Period Labor Units

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PREV_THIS_PER_LABOR_UNITS))

Fact - Primavera - Project History

Period Units

Previous This Period Nonlabor Units

Fact

The Nonlabor Units planned for the previous period

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.PREV_THIS_PER_NONLABOR_UNITS))

Fact - Primavera - Project History

Units

Remaining Labor Units

Fact

The remaining units for all labor resources assigned to the activity. The remaining units reflects the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the budgeted units. After the activity is completed, the remaining units are zero.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.REMAINING_LABOR_UNITS))

Fact - Primavera - Project History

Units

Remaining Late Labor Units

Fact

Remaining Late Labor Units

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.REMAINING_LATE_LABOR_UNITS))

Fact - Primavera - Project History

Units

Remaining Late Nonlabor Units

Fact

Remaining Late Nonlabor Units

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.REMAINING_LATE_NONLABOR_UNITS))

Fact - Primavera - Project History

Units

Remaining Nonlabor Units

Fact

The remaining units for all nonlabor resources assigned to the activity. The remaining units reflects the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the budgeted units. After the activity is completed, the remaining units are zero.

last(sum(Fact_W_WBS_HISTORY_F_Wbs_History.REMAINING_NONLABOR_UNITS))