Dimensions in Primavera Cloud - Project User Defined Fields
The following dimensions are included in the Primavera Cloud - Project User Defined Fields subject area:
Folder / Sub-Folder | Field Name | Description |
---|---|---|
Project Portfolio |
|
|
Project Portfolio | Project Portfolio Name | The name of the portfolio |
Project Portfolio | Project Portfolio Description | The description of the portfolio |
Project / General - (Project) |
|
|
Project / General - (Project) | Project Object Id | The Unique ID of the project |
Project / General - (Project) | Project ID | The Project Id of the project |
Project / General - (Project) | Project Name | The project name |
Project / General - (Project) | Added By | The name of the user who added the project |
Project / General - (Project) | Status | The status of the project as active, inactive, planned or what-if |
Project / General - (Project) | Overall Project Score | The Project score |
Project / General - (Project) | Schedule Health Score | Schedule Health Score |
Project / General - (Project) | Datasource Id | A unique source Id created for the data source being used. Used to identify data sources when using multiple data sources. |
Project / Dates - (Project) |
|
|
Project / Dates - (Project) | Anticipated Start | Anticipated start date of the project. |
Project / Dates - (Project) | Anticipated Finish | Anticipated finish date of the project. |
Project / Dates - (Project) | Data Date | The current data date for the project. The project status is up to date as of the data date. The data date is modified when project actuals are applied. |
Project / Dates - (Project) | Date Added | The date this project was added. |
Project / Dates - (Project) | Start | The current start date of the project. For a not started project, this is the project's planned start date. For a project that has started or is complete, this is the project's actual start date. For projects with no activities, the start date is equal to the anticipated start date if one is defined; if no anticipated start is defined, then the start date is equal to the project's planned start date. |
Project / Dates - (Project) | Finish | The current finish date of the project. For not started and in-progress projects, this is the latest early finish date from all activities in the project. For completed projects, this is the latest actual finish date derived from all activities. For projects with no activities, the Finish Date is equal to the Anticipated Finish date if one is defined. For projects with no activities and no Anticipated Finish date, the Finish Date field is blank. |
Project / Dates - (Project) | Forecast Start Date | The start date optionally used by the project scheduler. |
Project / Dates - (Project) | Forecast Finish Date | The end date optionally used by the project scheduler. |
Project / Dates - (Project) | Must Finish By | The optional date constraint you can specify for the project end date. |
Project / Dates - (Project) | Planned Start | The date the project is scheduled to start. |
Project / Dates - (Project) | Scheduled Finish | The calculated latest early finish date, which is based on the schedule most recently generated for the project. |
Project / Durations - (Project) |
|
|
Project / Durations - (Project) | Actual Duration | Actual duration is the total time from the project actual start date to the actual finish date (for completed projects), or to the current data date (for in-progress projects). |
Project / Durations - (Project) | At Completion Duration | The duration at completion is the total time from the project current start date to the current finish date. |
Project / Durations - (Project) | Baseline Duration | The duration of the baseline project. |
Project / Durations - (Project) | Planned Duration | Planned duration is the total time from the project planned start date to the planned finish date. |
Project / Durations - (Project) | Remaining Duration | Remaining duration is the total time from the current data date to the current finish date. |
Project / Durations - (Project) | Variance - Baseline Project Duration | The duration between the baseline project duration and the current project duration. Calculated as Planned Duration minus At Completion Duration. |
Location - (Project) |
|
|
Project / Location - (Project) | Location Name | The name of the location |
Project / Location - (Project) | Location Type | Location Type |
Project / Location - (Project) | Address Line 1 | The first line of the address |
Project / Location - (Project) | Address Line 2 | The second line of the address |
Project / Location - (Project) | City Name | The city name for this Location |
Project / Location - (Project) | Municipality Name | The municipality name for this Location |
Project / Location - (Project) | State Name | State/Province |
Project / Location - (Project) | Country Code | The country code for this Location |
Project / Location - (Project) | Postal Code | The postal code for this Location |
Project / Location - (Project) | Longitude | The longitude for this Location |
Project / Location - (Project) | Latitude | The latitude for this Location |
Project / Codes - (Project) |
| This folder displays a maximum of 300 Project codes that have been selected by your organization in the CIC Administration application. To include or exclude project codes, contact your CIC Analytics administrator. |
Project / Codes - (Project) | Project Code Id <n> where n= 01 to 300 | Project Code <n> where n = 1 to 300 |
Project / Codes - (Project) | Project Code Name <n> where n= 01 to 300 | Project Code <n> where n = 1 to 300 |
Project / Text UDFs - (Project) |
| This folder displays a maximum of 300 Project UDFs of Text data type that have been selected by your organization in the CIC Administration application. To include or exclude UDFs, contact your CIC Analytics administrator. |
Project / Text UDFs - (Project) | Project UDF Text <n> where n = 1 to 300 | Text Type Project UDF <n> where n = 1 to 300 |
Project / Date UDFs - (Project) |
| This folder displays a maximum of 300 Project UDFs of Date data type that have been selected by your organization in the CIC Administration application. To include or exclude UDFs, contact your CIC Analytics administrator. |
Project / Date UDFs - (Project) | Project UDF Date <n> where n = 1 to 300 | Date Type Project UDF <n> where n = 1 to 300 |