uuu_duration_baseline
Data Definition: Decimal Amount
Form Label (Field Label): Baseline Duration
# of Characters: Not applicable
Where to use it:
- Schedule Activity Attribute forms
- Schedule Sheets
Use this element for: Displaying the baseline duration of a project on the schedule sheet.
This element produces an automatic formula of: duration = finish - start.
This is one element of a set that includes uuu_start_baseline and uuu_finish_baseline. You must include all 3 of these elements on the form for the baseline function to work correctly.
As the designer, you can assign a name to the baseline; for example “Baseline Electrical.”