uuu_start_baseline[1...10]
Data Definition: Date Picker
Form Label (Field Label): Baseline [1...10] Start
# of Characters: Not applicable
Where to use it:
- Schedule Activity Attribute forms
- Schedule Sheets
- Resource Assignment Attribute Forms
Use this element for: Specifying the baseline start date of a project phase on a schedule sheet.
This is one data element of a set that includes:
- uuu_finish_baseline[1...10]
- uuu_duration_baseline[1...10]
- uuu_total_cost_baseline[1...10]
You must include all of these elements on the form for the baseline function to work correctly.
As the designer, you can assign a name to the baseline; for example “Baseline Electrical.”