Modifying Step Due Date

If the step duration and workflow override are enabled on the business process, you can also set the task due date for the next step.

To change the task due date

  1. In the Due Date Details section, click the Calendar icon. The Task Due Dates window opens.
  2. Choose one of the following options:
    • Set all task due dates as: Lets you set the same due date for all assignees.
    • Set individual task due dates: Allows you to assign different due dates for each assignee one at a time.
  3. Click the Calendar icon to set the due date. For the second option, click the date listed in the Task Due Date column.
  4. Select the month and year, and then click the date you want to select.

    Note: The workflow engine uses the company workday calendar. Grayed-out dates are those that have been set as non-working days (for example, weekends and holidays) by your company administrator. You cannot select non-working days for a task due date.

Editing the Due Date (due_date) Field

In the Workflow Settings field in the Workflow Setup of a BP, if the option Override Workflow Due Date field set as Yes, then you can edit the due date in the creation step.

In the Workflow Settings field in the Workflow Setup of a BP, if the option Override Workflow Due Date field set as No, then you cannot edit the due date in the creation step.

Also, you cannot edit the due date if: