Change Start Dates

You can change the start dates of planned projects, but not those in execution. When you change a start date, the system shifts the end date to preserve the project duration, and also shifts the cash flow numbers (excluding pre-actuals) left or right to preserve the cash flow distribution.

To change a start date

  1. Double-click the date in the Start Date column. The system displays a calendar.
  2. Choose the new date from the calendar.

    The system shifts the end date and the cash flow numbers to reflect the change.

How the System Distributes Cash Flow

The system stores all cash flow amounts by month in the database. The logic that the system uses to distribute cash flow dollars is rendered in monthly allocations and presented as follows:



Last Published Monday, August 28, 2023