Link Activities (Adding Dependencies)
You can link multiple activity sheets by selecting one or more activity sheets, right-click, and selecting the Link Selected Activities option. The selected activity sheets will be linked with the default relationship (Finish-to-Start) if no relationship exists.
The Predecessor and Successor columns in the Activity Sheet log show the activity sheets that are linked based on the Finish-to-Start relationship of the selected activity sheets. This setup will also reflect in the Gantt Chart.
Similarly, you can unlink the selected activity sheets by highlighting one or more activity sheets, right-click, and selecting the Unlink Selected Activities option. The Unlink Selected Activities option will be available only if the selected activity sheets are linked.
When you link multiple activity sheets (using the Link Selected Activities option):
- If the same relationship exists for all of the selected activity sheets, the system will not update any values.
- If the predecessor activity has been already added as successor for the highlighted row, the system will display an error message.
- If the successor activity has been already added as predecessor for the highlighted row, the system will display an error message.
- If you select a single activity sheet and try to link (using the Link Selected Activities option from Actions menu), the system will display an error message.