New and Existing Activities Through CSV Import

For the new activities with uuu_P6ActivityStatus as "Not Started" the following cases apply for Start, Finish, and Duration:

Note: Invalid values for any of the date and duration columns will result in error.

uuu_P6Start

uuu_P6Finish

uuu_P6Duration

uuu_P6PlannedStart

uuu_P6PlannedFinish

uuu_P6PlannedDuration

uuu_P6RemainingEarlyStart

uuu_P6RemainingEarlyFinish

uuu_P6RemainingDuration

Behavior after Import

No value entered

No value entered

No value entered

No value entered

No value entered

No value entered

No value entered

No value entered

No value entered

Activity will be created with default value as project Start date for Start, Finish, Planned Start, Planned Finish, Remaining EarlyStart, Remaining EarlyFinish.

Valid date entered >= Project Start Date

Valid date >=Project Start Date and > uuu_P6Start

Calculated field if not provided explicitly

If not provided then should show same as P6Start 

If not provided then should show same as P6Finish 

Duration calculated between planned start and Planned finish

If not provided then should show same as P6Start 

If not provided then should show same as P6Finish 

Duration calculated using remaining start and remaining finish

Activity will be created with duration calculated based  Start and Finish Dates

No date entered, then same as uuu_P6PlannedStart; otherwise, retain the date entered

No date entered, then same as uuu_P6PlannedFinish; otherwise, retain the date entered

Calculated field if not provided explicitly

Valid date entered >= Project Start Date

Valid date >= Project Start Date and uuu_P6PlannedStart

Duration calculated between planned start and Planned finish

No date entered, then same as uuu_P6PlannedStart; otherwise, retain the date entered

No date entered, then same as uuu_P6PlannedFinish; otherwise, retain the date entered

Duration calculated using remaining start and remaining finish

Activity will be created with duration calculated based Start and Finish Dates

No date entered, then same as uuu_P6RemainingEarlyStart; otherwise, retains the date entered

No date entered, then same as uuu_P6RemainingEarlyFinish; otherwise, retains the date entered

Calculated field if not provided explicitly

No date entered, then same as uuu_P6RemainingEarlyStart; otherwise, retains the date entered

No date entered, then same as uuu_P6RemainingEarlyFinish; otherwise, retains the date entered

Not applicable

Valid date entered >= Project Start Date

Valid date >= Project Start Date and uuu_P6RemainingStart

Duration calculated using remaining start and remaining finish

Activity will be created with duration calculated based Start and Finish Dates

The validations mentioned above will be applied to the following dates and durations:



Last Published Monday, August 28, 2023