Update Activities
uuu_P6Start | uuu_P6Finish | uuu_P6Planned Start | uuu_P6PlannedFinish | uuu_P6ActualStart | uuu_P6ActualFinish | uuu_P6RemainingEarlyStart | uuu_P6RemainingEarlyFinish | Behavior after import |
---|---|---|---|---|---|---|---|---|
For Not Started Activity: Valid date provided | No Change | No Change | No Change | No Value | No Value | No Change | No Change | Activity will be updated with uuu_P6Start update provided uuu_P6Finish will be calculated based on Start and duration All other dates - Planned Start, Planned Finish, Remaining Early Start and Remaining Early Finish will be updated same as Start and Finish Activity status will be "Not Started" |
No Change | Valid date provided | No Change | No Change | No Value | No Value | No Change | No Change | Activity will be updated with uuu_P6Finish and duration will be recalculated All other dates - Planned Start, Planned Finish, Remaining Early Start and Remaining Early Finish will be updated same as Start and Finish Activity status will be "Not Started" |
No Change | No Change | No Change | No Change | Valid Value entered | No Value | No Change | No Change | Activity will be updated with uuu_P6Start same as uuu_P6ActualStart Planned Start and Planned Finish will not be changed Remaining Early start will be same as uuu_P6ActualStart and Remaining Early Finish will be same as uuu_P6Finish Activity status will be "In progress" |
No Change | No Change | No Change | No Change | No Change | Valid date entered | No Change | No Change | Activity will be updated with uuu_P6Finish same as uuu_P6ActualFinish Planned Start and Planned Finish will not be changed Remaining Early start and Finish will not show any dates (empty) as the activity is completed Activity status will be "Complete" Activity percent will be 100% (one hundred percent) |
Note: When you change any of the above dates, the system updates the dates accordingly. For activities that are marked as "Not Started," the values for the Start, Finish, Planned Start, Planned Finish, Remaining Early Start, and Remaining Early Finish will be the same.
Last Published Monday, August 28, 2023