Add Start Milestone Activity
uuu_P6Start | uuu_P6Finish | uuu_P6Duration | Activity Status | Activity Type | uuu_P6ActualStart | uuu_P6ActualFinish | uuu_P6PercentComplete | Behavior |
---|---|---|---|---|---|---|---|---|
Valid date provided | No value | No value | No value | Activity type is provided as 'Start Milestone' | No value | No value | No value | Activity will be created as milestone with Activity Type selected as "Start Milestone" Activity Status will be "Not Started" uuu_P6Start and uuu_P6Finish will be the same date as given in input CSV for uuu_P6Start. uuu_P6Duration will be 0 (zero) |
No value | Valid date provided. | Valid value provided or not provided. | No value | Activity type is provided as 'Start Milestone' | No value | No value | No value | Activity will be created as milestone with Activity Type selected as "Start Milestone" Activity Status will be "Not Started" uuu_P6Start and uuu_P6Finish will be the same as uuu_P6Finish uuu_P6Duration will be 0 (zero) |
No value | No value | No value | Activity Status is provided as 'Not Started' | Activity type is provided as 'Start Milestone' | No value | No value | No value | Activity will be created as milestone with Activity Type selected as "Start Milestone" Activity Status will be "Not Started" uuu_P6Start and uuu_P6Finish will be the project schedule start date uuu_P6Duration will be 0 (zero) |
No value | No value | No value | Activity Status is provided as 'Completed' | Activity type is provided as 'Start Milestone' | No value | No value | No value | Activity will be created as milestone with Activity Type selected as "Start Milestone" Activity Status will be "Completed" uuu_P6Start and uuu_P6Finish will be the project schedule start date uuu_P6ActualStart and uuu_P6ActualFinish will be the project schedule start date uuu_P6Duration will be 0 (zero) uuu_P6PercentComplete will be 100 (one hundred) |
Valid date provided | Valid date provided and not same as uuu_P6start | Valid value provided or not provided. | No value | Activity type is provided as 'Start Milestone' | No value | No value | No value | Activity will be created as milestone with Activity Type selected as "Start Milestone" Activity Status will be "Not Started" uuu_P6Start and uuu_P6Finish will be the same date as given in input CSV for uuu_P6Start uuu_P6Duration will be 0 (zero) |
No Value | No Value | Valid value provided or not provided. | No value | Activity type is provided as 'Start Milestone' | No value | No value | No value | Activity will be created as milestone with Activity Type selected as "Start Milestone" Activity Status will be "Not Started" uuu_P6Start and uuu_P6Finish will be the same date as given project schedule start date uuu_P6Duration will be 0 (zero) |
Valid date provided | Valid date provided and not same as uuu_P6start or Value not provided | Valid value provided or not provided. | No value | Activity type is provided as 'Start Milestone' | No value | No value | No value | Error message Note: This is the same case when uuu_P6ActualStart and uuu_P6ActualFinish are provided, and they are different dates. |
Valid date provided | Valid date provided and same as uuu_P6start or Value not provided | No value | No value | Activity type is provided as 'Start Milestone' | Valid date provided | No value | No value | Activity will be created as milestone with Activity Type selected as "Start Milestone" Activity Status will be 'Completed'. uuu_P6ActualStart and uuu_P6ActualFinish will be same date as provided uuu_P6Start and uuu_P6Finish will be the same date as uuu_P6ActualStart uuu_P6Duration will be 0 (zero) uuu_P6PercentComplete will be 100 (one hundred) Activity will be created as milestone with Activity Type selected as "Start Milestone" Activity Status will be 'Completed'. uuu_P6ActualStart and uuu_P6ActualFinish will be same date as provided uuu_P6Start and uuu_P6Finish will be the same date as uuu_P6ActualStart uuu_P6Duration will be 0 (zero) uuu_P6PercentComplete will be 100 (one hundred) |
The following dates will show the same date as uuu_P6Start, uuu_P6Finish and uuu_P6Duration for the milestone activities:
- uuu_P6PlannedStart
- uuu_P6PlannedFinish
- uuu_P6PlannedDuration
- uuu_P6RemainingDuration
- uuu_P6RemainingEarlyFinish
- uuu_P6RemainingEarlyStart