Update Existing Activity (In Progress or Completed) to Start Milestone

uuu_P6Start

uuu_P6Finish

uuu_P6Duration

Activity Status

Activity Type

uuu_P6ActualStart

uuu_P6ActualFinish

uuu_P6PercentComplete

Behavior

Valid value provided  or not provided.

Valid value provided  or not provided.

Valid value provided  or not provided.

Valid value provided  or not provided.

Activity type is provided as  'Start Milestone'

Valid value provided  or not provided.

Valid value provided  or not provided.

Valid value provided  or not provided.

Activity will be created as milestone with Activity Type selected as "Start Milestone"

Activity Status will be "Completed"

uuu_P6Start and uuu_P6Finish will be the same date as uuu_P6ActualStart

uuu_P6Duration will be 0 (zero)

uuu_P6ActualStart and uuu_P6ActualFinish will be same date and uuu_P6ActualDuration will be 0 (zero)

uuu_P6PercentComplete will be 100 (one hundred)

Activity will be created as milestone with Activity Type selected as "Start Milestone"

Activity Status will be "Completed"

uuu_P6Start and uuu_P6Finish will be the same date as uuu_P6ActualStart

uuu_P6Duration will be 0 (zero)

uuu_P6ActualStart and uuu_P6ActualFinish will be same date and uuu_P6ActualDuration will be 0 (zero)

uuu_P6PercentComplete will be 100 (one hundred)